Nortec Industries Airfog Series installation manual Setting the System for Normal Operation

Page 39

(3)If the timer were set as in the above examples, the system would run for 4 hours, shut off for 2 minutes, run for another 4 hours, shut off for 2 minutes, and so on and so forth.

NOTE

The humidistat takes precedence over the timer for shutting down the system. If the humidistat reaches its set point, it will shut the system off regardless of the timer to prevent over humidifying the space.

(4)The factory default setting for the timer is 2 minutes of off time (cleaning time) after every 8 hours of operation. Using settings that result in an off time of less than 10 seconds are not recommended. As well, using settings that result in an on time of less than 15 minutes are not recommended.

E.SETTING THE SYSTEM FOR NORMAL OPERATION

(1)Once the start-up and adjustment, and configuration procedures have been completed the unit is ready to operate normally. The following steps complete the start-up procedures:

(a)Close and lock all covers including the control panel covers.

(b)Tighten the lock nuts on the primary air and water regulators.

(c)Set the humidistat to the desired level.

(2)The AirFog humidification system is now ready to operate normally.

10-30

Page 32 2008-04-11

Image 39
Contents Airfog SeriesTM Proprietary Notice Liability Notice Table of Contents SHUT-DOWN Procedure List of Figures List of Tables This page Intentionally Left Blank Introduction Introduction General Airfog Technical Considerations Older Nortec Airfog System Components 10-00 This page Intentionally Left Blank Installation Nozzle System Layout InstallationTypical Nozzle Layout for Wall Mounted System Multi Zone Layout Mounting of Nozzles CleaningIntroduction Supply Feed LinesWater and Air Line Pressure Control Saddle Clamp Installation Connecting NozzlesPilot Operated AIR Regulator Vacuum Valve10-10 Vacuum Valve Operation Control Panel Electrical WiringPrimary AIR Pressure Control Primary Water Pressure ControlPrimary Air Pressure Control Section Pilot Lines Schematic Plumbing LayoutThis page Intentionally Left Blank Mini & Octo Installation AFE Mini Systems AFE Self Contained Airfog SystemsMini Installations AFE Octo Systems Installation ProcedureOcto Layout with Interfaces 10-20 Ceiling Mounting of Octo Four Octo Units with a Single Control Panel START-UP Procedure Water Supply Compressed AIR SupplySelf Cleaning Cycle Adjustment Setting the System for Normal Operation Capacity Output vs. Vacuum Valve Adjustment This page Intentionally Left Blank 10-40 SHUT-DOWN ProcedureAFE, MINI, and Octo Shut Down Procedures 10-50 MaintenanceMaintenance Unscheduled Maintenance 10-50 10-60 TroubleshootingTroubleshooting 10-60 This page Intentionally Left Blank 10-70 Spare PartsSpare Parts Octo Exploded View Octo This page Intentionally Left Blank Item # Description QTY Vacuum Valve Exploded View Item # Description Octo Mini Standard Control Panel Exploded View AFE This page Intentionally Left Blank Warranty Authorized Agent