STEP 5 — CALIBRATE

CALIBRATION PROCEDURE

WARNING: The calibration procedure requires about 5 minutes to complete. If gas is not applied at the appropriate time, a calibration failure may occur (refer to "Calibration Failure" on page 14 for specific information).

For accurate performance, the concentration of gas, corresponding to 0 to 25% oxygen is converted to a linear 4 to 20 mA output signal which can be powered from the primary dc supply of the instrument. Power up the unit for at least 4 hours BEFORE first calibration.

The following calibration procedure should be followed to ensure an accurate correlation between the 4 to 20 mA output signal and the gas concentration.

Calibration Procedure

1.Confirm successful power up of ControllerLED Green Blip/blink every 2 seconds; no fault indicated.

2.Flow certified ZERO AIR at a rate of 0.5 litres per minute through the calibration cup for 1 minute to ensure clean air environment.

3.Use the Calibration Button or Reed Switch to access the Main Menu and wait for countdown to complete.

4. When Calibrate Sensor YES? displays, use the Calibration Button or Reed Switch to select YES? Selection will be confirmed by a flashing YES .

5.When Apply Clean Air displays apply clean air.

6.When Apply 20.9% O2 displays, apply O2 at a rate of 0.5 litres per minute using the calibration cup.

7.The display will show Calibrating as the internal settings are being modified (current loop 3.3 mA).

8.Remove span gas when the message Remove Gas displays (Status LED Green solid and 3.6 mA output).

9.The message Cal Complete will display when calibration is complete.

10.Apply zero gas (clean air) again to purge system.

Note: Always apply test gas after calibration to verify operation.

Figure 13: Calibration Procedure

Display

Calibrate

Apply Clean

Apply 20.9%

 

 

 

Shows

Sensor YES?

Air

O2

Calibrating

Remove Gas

Cal Complete

 

 

 

 

 

 

 

 

Action

Select YES?

Apply clean

Apply O2

 

Remove gas

 

 

 

 

 

(zero air)

 

 

 

 

MLP-A/AR/AD-ST1400-25

13

Image 18
Contents Millennium Page Warranty Contact InformationImportant Information Table of Contents How to Return Equipment MaintainManual SensorController ProductPlan Locate CONTROLLER/SENSOROption Install UnpackExternal Equipment Field Installation WireConnecting Wires MountElectromechancial Relay Board Board AssemblySolid State Relay Board Modbus TerminalsRS-485 Communication Sensor Board Terminals Controller WireTerminal Board Power Controller Sensor and ControllerWiring-Sensor Separation Sensor SeparationNON-ISOLATED/ISOLATED Wiring Terminal ConnectionCurrent Output Remote Reset Modbus TerminationOperate Scrolling 8-character displayRTU Registers Calibration ButtonStatus LED State Current O/P Accessing the Main Menu Magnetic Reed SwitchPower Up Current Loop Measurement Test JacksDisplay Calibration ProcedureCalibrate ShowsReview Relay Settings MonitorCalibration Failure Model Number Low High Fault Setting Relay OptionsAlarm Levels Relay Coil Status Millennium Relay OptionsBaud Rate Set Low Power Options OptionalNode Address Modbus OptionsRemote Reset Sensor FaultManual Reset Non-standard O2 LevelsModbus MaintainRelays Optional CurrentT1Y 7J7 Spare PARTS/ACCESSORIESDescription Net Safety Part Number Face Rotation OptionRotate PCB Assembly Appendix aAppendix B Resistance Table in Ohms Sensor Specifications Sensor Element