Crown Boiler KSZ175, KSZ150, KSZ125, KSZ200, KSZ120, KSZ065, KSZ090, KSZ100 VII System Piping, 1211

Page 12

VII System Piping

CAUTION

INSTALL BOILER SO THAT ALL ELECTRICAL COMPONENTS ARE PROTECTED FROM WATER (DRIPPING, SPRAYING, RAIN, ETC.) DURING APPLIANCE OPERATION AND SERVICE.

OPERATION OF THIS BOILER IN A SYSTEM HAVING SIGNIFICANT AMOUNTS OF DISSOLVED OXYGEN CAN CAUSE SEVERE HEAT EXCHANGER CORROSION DAMAGE.

Figure 10 shows recommended near boiler Piping for most common types of gravity return steam systems. Additional information on steam system design may be found in Installation Guide for Residential Hydronic Heating Systems (Pub. #200) published by the Hydronics Institute in Berkeley Heights, NJ.

One of the primary purposes of this near boiler piping is to separate tiny water droplets from the steam exiting the boiler so that “dry” steam is sent to the system. If the near boiler piping is not correct, wet steam will enter the system and the following problems may occur:

Short cycling on low water

Boiler or system Flooding

Hammering

Failure to heat one or more radiators

Avoid the common piping mistakes shown in Figure 11. This applies even if the existing boiler has one of the piping mistakes shown in Figure 11 and appears to be working. If two or more steam mains must be connected to the boiler, connect a separate take-off for each main into the header between the riser(s) and equalizer. Also note the following points:

1)A size reduction must be made to connect the header to the equalizer. This reduction must be made in the vertical equalizer line. Do not make this size reduction in the horizontal header.

FIGURE 10: STEAM BOILER PIPING FOR GRAVITY RETURN

1211

Image 12
Contents Crown Table of Contents Product DescriptionIII Before Installing General SpecificationsIV Locating the Boiler Air for Combustion and VentilationSide View For Buildings of Other than Unusually Tight Construction Boiler Installed in Confined Space ALL AIR from Inside ALL AIR from OUTDOORS, Using Openings Into Boiler Room Page VI Venting 109Minimum Recommended Breeching Chimney Size 1110VII System Piping 1211Piping Installation 1312Viii Indirect & Tankless Water Heater Piping Tanklessheaterpiping 1615 TanklessheaterpipingIX Fuel Line Piping 17161817 TWO-PIPE Gravity Feed System1918 Wiring 2019Indirect Water Heater Field Wiring 2120Feeder WIRINGMCDONNELL&MILLER#67LWCO 2322XI Start-up and Checkout 24232425 2526 XII Service and Maintenance 27262827 Tankless Heater Maintenance 2928Avoid Breathing Fiber Particulates and Dust 3029Installation Notes And Service Log 31303231 KEY # Description QTY. orPage 3433 KEY # DescriptionPage Rev 9