Crown Boiler KSZ075, KSZ150, KSZ125, KSZ200, KSZ175, KSZ120, KSZ065, KSZ090 IX Fuel Line Piping, 1716

Page 17

IX Fuel Line Piping

Fuel line piping design, materials and constructions must be in accordance with local building codes, requirements of the local authority having jurisdiction, and the latest edition of Installation of Oil-Burning Equipment (ANSI/NFPA 31). Refer also to the instruction manuals provided with the burner and oil pump.

Depending on the location of the fuel oil storage tank in relation to the oil burner, there are four types of oil piping systems generally being used:

a)ONE-PIPE GRAVITY SYSTEM - used when a fuel oil storage tank is positioned above an oil burner fuel pump. See Figure 13. A vertical distance from top of the tank to center line of the pump (Dimension ‘H’) over 8 feet will result in a pump inlet pressure in excess of the 3-psi limit in NFPA-31.

b)ONE-PIPE LIFT SYSTEM (not recommended) - Used when a fuel oil storage tank is located below an oil burner fuel pump. See Figure 14. The vertical distance from bottom of the tank to center line of the pump (Dimension ‘H’) must not exceed that shown in the pump manufacturer’s instructions. Although all oil piping systems must be airtight, one- pipe lift systems are particularly susceptible to nuisance lockout problems if the suction line is not completely airtight. A two-pipe lift system is therefore recommended over a one-pipe lift system.

FIGURE 13: ONE-PIPE GRAVITY SYSTEM

FIGURE 14: ONE-PIPE LIFT SYSTEM

1716

Image 17
Contents Crown Product Description Table of ContentsGeneral Specifications III Before InstallingAir for Combustion and Ventilation IV Locating the BoilerSide View For Buildings of Other than Unusually Tight Construction Boiler Installed in Confined Space ALL AIR from Inside ALL AIR from OUTDOORS, Using Openings Into Boiler Room Page 109 VI Venting1110 Minimum Recommended Breeching Chimney Size1211 VII System Piping1312 Piping InstallationViii Indirect & Tankless Water Heater Piping Tanklessheaterpiping Tanklessheaterpiping 16151716 IX Fuel Line PipingTWO-PIPE Gravity Feed System 18171918 2019 Wiring2120 Indirect Water Heater Field WiringFeeder 2322 WIRINGMCDONNELL&MILLER#67LWCO2423 XI Start-up and Checkout2425 2526 2726 XII Service and Maintenance2827 2928 Tankless Heater Maintenance3029 Avoid Breathing Fiber Particulates and Dust3130 Installation Notes And Service LogKEY # Description QTY. or 3231Page KEY # Description 3433Page Rev 9