2)One-pipe steam systems require air vents on each radiator, as well as at the end of each main. For the system to work properly, these vents must be properly installed, sized, and be in good condition. Inspect and replace any defective vents. If there are no vents at the ends of the mains, install them.

3)Do not attempt to manifold multiple KSZ boilers with gravity returns.

4)For installations with condensate or boiler feed pumps, follow the pump manufacturer’s piping instructions. Such systems generally do not require Hartford loops.

5)Do not use a check valve in place of, or in addition to, a Hartford loop on a gravity return system.

6)Pipe the fill connection from a clean source of cold water. When the water supply is from a well, make sure that a strainer is installed in the well system.

Piping Installation

1)Remove parts bag from boiler crate.

2)Install safety valve (spindle must be in vertical position) into the 3/4” tapping on top of the boiler.

3)Pipe the discharge of the safety relief valve to a location where water or steam will not create a hazard or cause property damage if the valve opens. The end of the discharge pipe must terminate in an unthreaded pipe. If the safety valve discharge is not piped to a drain, it must terminate at least 6 inches above the floor. The termination of the safety valve discharge piping must be in an area where it is not likely to become plugged by debris or subjected to freezing.

4)Install drain valve provided into the return piping.

5)Connect system supply and return to boiler. See Figure 10. All KSZ boilers use one supply riser and one return tapping.

DANGER

PIPE RELIEF VALVE TO A SAFE LOCATION

DO NOT INSTALL A VALVE IN THE RELIEF VALVE DISCHARGE LINE

DO NOT MOVE RELIEF VALVE FROM FACTORY SPECIFIED LOCATION

DO NOT PLUG RELIEF VALVE DISCHARGE

WRONG - TAKE-OFF BULLHEADED

INTO TWO MAINS

WRONG - HEADER BULLHEADED

INTO TAKE-OFF AND EQUALIZER

FIGURE 11: COMMON NEAR-BOILER PIPING MISTAKES

1312

Image 13
Contents Crown Product Description Table of ContentsGeneral Specifications III Before InstallingAir for Combustion and Ventilation IV Locating the BoilerSide View For Buildings of Other than Unusually Tight Construction Boiler Installed in Confined Space ALL AIR from Inside ALL AIR from OUTDOORS, Using Openings Into Boiler Room Page 109 VI Venting1110 Minimum Recommended Breeching Chimney Size1211 VII System Piping1312 Piping InstallationViii Indirect & Tankless Water Heater Piping Tanklessheaterpiping Tanklessheaterpiping 16151716 IX Fuel Line PipingTWO-PIPE Gravity Feed System 18171918 2019 Wiring2120 Indirect Water Heater Field WiringFeeder 2322 WIRINGMCDONNELL&MILLER#67LWCO2423 XI Start-up and Checkout2425 2526 2726 XII Service and Maintenance2827 2928 Tankless Heater Maintenance3029 Avoid Breathing Fiber Particulates and Dust3130 Installation Notes And Service LogKEY # Description QTY. or 3231Page KEY # Description 3433Page Rev 9