VII Gas Piping

Gas piping to the boiler must be sized to deliver adequate gas for the boiler to fire at the nameplate input at a line pressure between the minimum and maximum values shown on the rating plate. For more information on gas line sizing, consult the utility or Chapter 2 of the National Fuel Gas Code.

Figure 10 shows typical gas piping connection to the BSI boiler. A sediment trap must be installed upstream of all gas controls. Install a manual shut-off valve outside the jacket and ground joint union as shown.

The boiler and its gas connection must be leak tested before placing the boiler in operation. When doing this, the boiler and its individual shut-off must be disconnected from the rest of the system during any pressure testing of that system at pressures in excess of 1/2 psi. When pressure testing the gas system at pressures of 1/2 psi or less, isolate the boiler from the gas supply system by closing its individual manual shut-off valve.

*

FIGURE10: GASCONNECTIONTOBOILER

*State of Massachusetts Requires Manual Shut-off Valve to be “T” Handle Type

12

11

Image 12
Contents BSI Series Table of Contents Product DescriptionII Specifications BSI SpecificationsIII Before Installing IV Locating the BoilerAir for Combustion and Ventilation For Buildings of Other than Unusually Tight Construction ForBuildingsofUnusuallyTightConstructionBOILERINSTALLEDINCONFINEDSPACE, ALL AIR from Inside ALL AIR from OUTDOORS, Using Openings Into Boiler Room VI Venting Removing an Existing Boiler from a Common Chimney BSI Boilertypicalventsystem Installation and Components VII Gas Piping GasconnectiontoboilerViii System Piping General Piping NotesPipingInstallation Common NEAR-BOILER Piping Mistakes IX Indirect Water Heater Piping Indirectwater Heater BOILER-SIDE PipingWiring Indirect Water Heater Wiring Wiring Indirectwater Heater to Boiler BSI Control System Sequence of Operation Sequence of Operation, Standing PilotVent Damper Note Less Vent GAS Valve BSI379 Honeywell VR8204/VR8304 Series GAS Valves BSI069 Robertshaw XI Start-up and Checkout 2423Standing Pilot Burner Flame For Your Safety Read Before Operating For Your Safety Read Before Lighting For Your Safety Read Before Lighting Position Indicator High Altitude Burners GASVALVEDETAIL-HONEYWELLVR8200ORVR8300STANDINGPILOT XII Service and Maintenance On a continuous basisOn at least a weekly basis On an annual basisPage Heat Exchanger Cleaning Procedure Xiii Troubleshooting Start END Start END Standing Pilot Ignition System Troubleshooting Chart Intermittent Ignition System Troubleshooting Chart XIV Parts Page KEY # Page Boilers only Page Appendix a Knockdown Boiler Assembly Instructions Before InstallingFIGUREA1 BASE, Heat EXCHANGER, Flue Collector Assembly Gas Valve Installation Figure A2 Jacket Installation Electrical Wiring Connections Complete InstallationFigure A3 Tapping Locations see Text for Tapping Uses Crown