A.O. Smith HYB-90N Recommended Brush* Size For Primer And Cement Applications, Step A, Step B

Page 29
RECOMMENDED BRUSH* SIZE FOR PRIMER AND

PRIMER

It is recommended that Tetrahydrofuran (THF) be used to prepare the surfaces of pipe and fittings for solvent welding. Do not use water, rags, gasoline or any other substitutes for cleaning PVC or CPVC surfaces. A chemical cleaner such as MEK may be used.

CEMENT

The cement should be a bodied cement of approximately 500 to 1600 centipoise viscosity containing 10-20% (by weight) virgin PVC material solvated with tetrahydrofuran (THF). Small quantities of dimethyl formamide (DMF) may be included to act as a retarding agent to extend curing time. Select the proper cement; Schedule 40 cement should be used for Schedule 40 pipe. Never use all-purpose cements, commercial glues and adhesives or ABS cement to join PVC or CPVC pipe and fittings.

APPLICATORS

Select a suitable pure bristle type paint brush. Use a proper width brush or roller to apply the primer and cement (see chart below). Speedy application of cement is important due to its fast drying characteristics. IMPORTANT NOTE: A dauber type applicator should only be used on pipe sizes 2 in. and below. For larger diameter pipe, a brush or roller must be used.

RECOMMENDED BRUSH* SIZE FOR PRIMER AND

CEMENT APPLICATIONS

Nominal Pipe (IPS)

Size Brush Width

2

1.5 in. (3.8cm)

3

1.5”-2.5 in. (3.8cm -

 

6.4cm)

*USE ONLY NATURAL BRISTLE 3. MAKING THE JOINT.

A.Cutting

Pipe must be squarely cut to allow for the proper interfacing of the pipe end and the fitting socket bottom. This can be accomplished with a miter box saw or wheel type cutter Wheel type cutters are not generally recommended for larger diameters since they tend to flare the corner of the pipe end. If this type of cutter is used, the flare on the end must be completely removed.

NOTE: Power saws should be specifically designed to cut plastic pipe.

STEP A

B.Deburring

Use a knife, plastic pipe deburring tool, or file to remove burrs from the end of small diameter pipe. Be sure to remove all burrs from around the inside as well as the outside of the pipe. A slight chamfer (bevel) of about 10°-15° should be added to the end to permit easier insertion of the pipe into the end of the fitting. Failure to chamfer the edge of the pipe may remove cement from the fitting socket, causing the joint to leak.

STEP B

C.Test dry fit of the joint

Tapered fitting sockets are designed so that an interfaced fit should occur when the pipe is inserted about 1/3 to 2/3 of the way into the socket. Occasionally, when pipe fitting dimensions are at the tolerance extremes, it will be possible to fully insert dry pipe to the bottom of the fitting socket. When this happens, a sufficient quantity of cement must be applied to the joint to fill the gap between the pipe and fitting. The gap must be filled to obtain a strong, leak-free joint.

www.hotwater.com

29

Image 29
Contents POWER VENT GAS MODELS For Your SafetyInstallation and Operating Manual HYBRID GAS WATER HEATERSIMPORTANT INFORMATION TABLE OF CONTENTSIMPORTANT DEFINITIONS SAFE INSTALLATION, USE AND SERVICEGENERAL SAFETY DANGER INTRODUCTION Page GET TO KNOW YOUR WATER HEATER - GAS MODELS REPLACEMENT PARTS AND DELIMING PRODUCTSROUGH IN DIMENSIONS INSTALLATION CONSIDERATIONSINSTALLATION REQUIREMENTS FOR THE COMMONWEALTH OF MASSACHUSETTS Water Potable Heating All models are considered WATER PIPING - MIXING VALVE USAGEFACTS TO CONSIDER ABOUT LOCATION HANDLE INSTALLATION Access To EARTHQUAKE ZONESTop Casing Front ScrewsAPPLIANCES IN CONFINED SPACES COMBUSTION AIR AND VENTILATIONAPPLIANCES IN UNCONFINED SPACES B. ALL AIR FROM OUTDOORS See Figures 12, 13 and WATER PIPING CHEMICAL VAPOR CORROSIONCLOSED WATER SYSTEMS THERMAL EXPANSIONTEMPERATURE-PRESSURE RELIEF VALVE HARD WATERT&P Valve and Pipe Insulation if supplied SEDIMENT TRAPS GAS PIPINGGAS LINE PURGING HIGH ALTITUDE INSTALLATIONSFLOODING/FREEZING FILLING THE WATER HEATERPLANNING THE VENT SYSTEM If using 2 inch vent pipeVENT PIPE TERMINATION RODENT SCREEN INSTALL INTO ELBOW GROUND LEVEL OR MAXIMUM SNOW LINE If using 3 inch vent pipeTERMINATION ELBOW ELBOW STRAPVENT TERMINAL INSTALLATION, SIDEWALL INSTALLATION OF VENT SYSTEMCONDENSATE CONDENSATION WARNINGVent terminals supplied with heater must be used SEQUENCE OF INSTALLATIONSINSTALLATION SEQUENCE INSTALLATION OF VERTICAL VENT SYSTEM INSTALLATION OF VENT SYSTEM, SIDEWALLVENT PIPE PREPARATION STEP B RECOMMENDED BRUSH* SIZE FOR PRIMER AND CEMENT APPLICATIONSSTEP A STEP E U.S. POWER VENTSTEP F STEP G CONNECTION TO VENT PIPEVENT HOODS MAY BE EXTREMELY HOT DURING OPERATION CALIBRATION ELECTRICAL CONNECTIONSFIGURE 33a “OFF”, “up”DISPLAY PANEL OPERATING INSTRUCTIONSNumeric Display DISCONNECTION WHEN SERVICING CAUTION LABEL ALL WIRES PRIOR TOCONTROLS. WIRING ERRORS CAN CAUSE IMPROPER AND DANGEROUSFOR YOUR SAFETY READ BEFORE LIGHTING LIGHTING INSTRUCTIONSOPERATING INSTRUCTIONS TO TURN OFF GAS TO APPLIANCEDESCRIPTION HEAT CYCLE DEFINITIONSSTATE TEMPERATURE REGULATION Temperature Probes UNIQUE HYBRID FEATURESWater Circulation Pump Line Voltage Monitor Detection of Failure to Maintain Desired Constant Temperature CONSTANT OUTPUT TEMPERATURE CONTROLSTART UP CONDITIONS OPERATIONAL CONDITIONSHOUSEKEEPING MAINTENANCEVENTING SYSTEM INSPECTION BURNER OPERATION AND INSPECTIONCLEANING THE INLET WATER FILTER ANODE ROD REPLACEMENTTEMPERATURE-PRESSURE RELIEF VALVE OPERATION MOTORSFLUSHING THE HEAT EXCHANGER LIME BUILD- UP CLEANING THE HEAT ENGINEDRAINING THE TANK FAULT INDICATION AND ERROR CODESDiagnostic DIAGNOSTIC DISPLAYCode and DisplayedLockout FaultCause RemedyLockout FaultCode DescriptionLockout TROUBLESHOOTING Check if there is any error code on WHEN THE TAP IS OPENEDb.The unit display is an error code system installed, or there is aLEAKAGE CHECKPOINTS SERVICEA Baffle, Flue B Hot Water Outlet Nipple w/ Anode, Heat Trap PARTS IDENTIFICATIONITEM # AB C DEF G T SH R I Q P KIT # REPLACEMENT PARTS DESCRIPTIONSERVICE AND LABOR RESPONSIBILITY LIMITED RESIDENTIAL GAS WARRANTYCLAIM PROCEDURE CONDITIONS AND EXCEPTIONSPage Page 500 TENNESSEE WALTZ PARKWAY ASHLAND CITY, TN PHONE 1-800-433-2545 FAX