LEVELING

length and width at least 2" greater than the diameter of the heater and must be piped to an adequate drain. The pan must not restrict combustion air flow.

LEVELING

If the unit is not level, insert the bolts which were used in crating into the legs to correct this condition.

CLEARANCES

These heaters are approved for installation on combustible flooring (with Leg Kit #6570-7) in an alcove when the minimum clearance from any combustion construction are followed as indicated in figure 5 and Table 4.

In all installations the minimum combustible clearances from vent piping shall be 6" (152mm). Vent piping passing through a combustible wall or ceiling must be a continuous run (no joints) and retain the 6" (152mm) clearance unless an approved reducing thimble is used.

A service clearance of 24" (610mm) should be maintained from serviceable parts, such as relief valves, flue baffles, thermostats, cleanout openings or drain valves.

The units are approved for installation with side, rear and ceiling clearances as indicated below:

MINIMUM CLEARANCES TO COMBUSTIBLES IN INCHES (mm)

 

MODEL

”A”

”B”

”C”

”D”

 

 

RIGHT

LEFT

BACK

CEILING

 

 

SIDE

SIDE

 

 

 

BTN-120

2” (51mm)

2” (51mm)

2” (51mm)

12” (305mm)

 

BTN-154

2” (51mm)

2” (51mm)

2” (51mm)

12” (305)

 

BTN-180

2” (51mm)

2” (51mm)

2” (51mm)

12” (305)

 

BTN-199

2” (51mm)

2” (51mm)

2” (51mm)

12” (305)

 

BTN-200/A

2” (51mm)

2” (51mm)

2” (51mm)

12” (305)

 

BTN-250/A

2” (51mm)

2” (51mm)

2” (51mm)

12” (305)

 

BTN-275/A

2” (51mm)

2” (51mm)

2” (51mm)

12” (305)

 

BTN-310/A

3” (76mm)

3” (76mm)

3” (76mm)

12” (305)

 

BTN-366/A

6” (152mm)

6” (152mm)

6” (152mm)

12” (305)

 

BTN-400/A

3” (76mm)

3” (76mm)

3” (76mm)

12” (305)

TABLE 4

CLEARANCES TO NONCOMBUSTION CONSTRUCTION

MODEL

”A”

”B”

”C”

”D”

 

 

RIGHT

LEFT

BACK

CEILING

 

SIDE

SIDE

 

 

 

 

BTN-120

0

0

0

12” (305mm)

 

 

BTN-154

0

0

0

12” (305mm)

BTN-180

0

0

0

12” (305mm)

BTN-199

0

0

0

12” (305mm)

BTN-200/A

0

0

0

12” (305mm)

BTN-250/A

0

0

0

12” (305mm)

BTN-275/A

0

0

0

12” (305mm)

BTN-310/A

6” (152mm)

6” (152mm)

6” (152mm)

12” (305mm)

BTN-366/A

0

0

0

12” (305mm)

BTN-400/A

0

0

0

12” (305mm)

TABLE 5

HARD WATER

Where hard water conditions exist, water softening or the threshold type of water treatment is recommended. This will protect the dishwashers, coffee urns, water heaters, water piping and other equipment.

See MAINTENANCE section for details of tank cleanout procedure.

AIR REQUIREMENTS

REFER TO THE LATEST EDITION OF THE "NATIONAL FUEL GAS CODE" ANSI Z223.1/NFPA 54.

KEEP APPLIANCE AREA CLEAR AND FREE OF COMBUSTIBLE MATERIALS, GASOLINE AND OTHER FLAMMABLES, VAPORS AND LIQUIDS.

DO NOT OBSTRUCT THE FLOW OF COMBUSTION OR VENTILATING AIR.

CLEARANCES WARNING

FOR SAFE OPERATION PROVIDE ADEQUATE AIR FOR COMBUSTION AND VENTILATION. AN INSUFFICIENT SUPPLY OF AIR WILL CAUSE RECIRCULATION OF COMBUSTION PRODUCTS RESULTING IN AIR CONTAMINATION THAT MAY BE HAZARDOUS TO LIFE. SUCH A CONDITION OFTEN WILL RESULT IN AYELLOW, LUMINOUS BURNER FLAME, CAUSING CARBONING OR SOOTING OF THE COMBUSTION CHAMBER,

ILLUSTRATION OF MINIMUM COMBUSTIBLE CLEARANCES INANALCOVE - FIGURE 5

7

Image 7
Contents MODELS BTN 120 THRU 400/A Series INSTALLATION OPERATION MAINTENANCE LIMITED WARRANTYCOMMERCIAL GAS, GLASS-LINED, TANK-TYPE WATER HEATER FRONT VIEW ROUGH-IN-DIMENSIONSTABLE 1. ROUGH-IN-DIMENSIONS TABLE 3. GASAND ELECTRICAL CHARACTERISTICSFOREWORD TABLE OF CONTENTSCHEMICAL VAPOR CORROSION GENERAL SAFETY INFORMATIONPRECAUTIONS GROUNDING INSTRUCTIONSELECTRONIC IGNITION CONTROL FEATURESHIGH ALTITUDE INSTALLATIONS HIGH LIMIT SWITCHLOCATING THE HEATER CIRCULATING PUMPDISHWASHING MACHINE REQUIREMENT UNCRATINGAIR REQUIREMENTS LEVELINGCLEARANCES HARD WATERCONFINED SPACE VENTINGMULTIPLE HEATER MANIFOLD UNCONFINED SPACETYPE B GAS VENT Multiple Gas Fired Tank-Type Heaters TABLE 6. TECHNICAL DATA VENTINGTABLE 6. TECHNICAL DATA VENTING Continued RELIEF VALVE WATER LINE CONNECTIONSWATER POTABLE HEATING AND SPACE HEATING See pages THERMOMETERS Not SuppliedDANGER INSTALLATION DIAGRAMS-TOP INLET/OUTLET USAGEGENERAL CODE RESTRICTIONSTEMPERATURE AT FIXTURES. SEE WATER TEMPERATURE CONTROL VERTICAL STORAGE TANK AND FORCED CIRCULATIONHORIZONTAL STORAGE TANK AND FORCED CIRCULATION TEMPERATURE SETTING SHOULD NOT EXCEED SAFE USEWITH RECIRCULATION OF SANITIZING LOOP TWO TEMPERATURE - ONE HEATER HIGH TEMPERATURE STORAGETWO TEMPERATURE - TWO HEATERS, ONE PRE-HEATER/ONE - BOOSTER HEATER INSTALLATION DIAGRAMS-SIDE INLET/OUTLET USAGEWITH OR WITHOUT BUILDING RECIRCULATION HEATER WITH MIXING VALVE AND RECIRCULATED SANITIZING LOOP ONE OR TWO TEMPERATURE - ONE HEATERS,HIGH TEMPERATURESTORAGE WITH OR WITHOUT RECIRCULATION HEATER WITH OR WITHOUT MIXING VALVETWO PRE-HEATERS WITH BOOSTER HEATER TWO TEMPERATURE - TWO PRE-HEATERS WITH MIXING VALVE OR BOOSTERHEATER WITH OR WITHOUT BUILING RECIRCULATION TWO PRE-HEATERS WITH MIXING VALVEHORIZONTAL STORAGE TANK MEDIUM TEMPERATURE - ONE HEATER WITH AUXILIARY STORAGE TANK FORCEDCIRCULATION WITH OR WITHOUT BUILDING RECIRCULATION VERTICAL STORAGE TANKFOUR UNIT MANIFOLD KIT MANIFOLD KITSTWO UNIT MANIFOLD KIT THREE UNIT MANIFOLD KITFIGURE 9 - SINGLE UNIT WIRING DIAGRAM BTN-120 THROUGH 400A HEATER WIRINGCUBIC FEET PER HOUR GAS PIPINGGAS PRESSURE REGULATOR TABLE 7 - GAS SUPPLY LINE SIZES IN INCHES MAXIMUM CAPACITY OF PIPE IN1 CU. FT. OF GAS AT FULL CAPACITY OPERATIONMANIFOLD GAS PRESSURE IN INCHES OF WATER COLUMN ALL MODELS APPROXIMATE TIME REQUIRED TO CONSUMESEQUENCE OF OPERATION LIGHTING AND OPERATION INSTRUCTIONS FOR YOUR SAFETY READ BEFORE OPERATINGOPERATING INSTRUCTIONS WATER TEMPERATURE CONTROL PREVENTIVE MAINTENANCECHECK THE IGNITOR ASSEMBLY IGNITOR ASSEMBLYFIGURE 11, IGNITOR MAIN BURNERGAS VALVES CHECKING THE INPUTANODE ROD INSPECTION VENTING SYSTEMREMOTE STORAGE TANK TEMPERATURE CONTROL HOT WATER ODORDELIMING USING FLO-JUG METHOD RECOMMENDED PROCEDURE FORTANK CLEANOUT PROCEDURE DELIMING SOLVENTSELECTRICAL SERVICING SERVICESYSTEM DIAGNOSTICS IGNITION MODULE SYSTEMSEQUENCE OF OPERATION FLOW CHART REPLACEMENT PARTS, SERVICE HANDBOOKS AND TRAINING AIDSREPLACEMENT PARTS COMPLAINT OPERATIONAL CHECKLISTSERVICEMAN REMEDYKEEPTHISWARRANTYPOSTEDADJACENTTOTHEHEATERFORFUTUREREFERENCE Model BTN Limited Warranty4. SERVICEANDREPAIREXPENSES 6. CLAIMPROCEDURE