START-UP OF UNIT

Follow the procedures for the initial and consequent operations of the unit.

1.Make sure that all the switches on the control panel, such as the power switch, the remote alarm switch, the back-up system switch (AT type only) are off.

2.Liquid CO2 gas cylinder for AT type is set at this time.

3.Shut the door and connect the power cable to the power supply after the inner lid is installed.

4.Turn on the power supply switch and the temperature is displayed on the digital indicator.

5.Set the desired chamber temperature by using the keypads on the control panel. Do not set the chamber temperature at lower than -90oC.

6.Set the temperature at which the back-up system activates according to the procedure on page 20 when the temperature display pointer of temperature recorder corresponds with the desired temperature if the back-up system is used. (AT type only)

7.Switch on the remote alarm switch and CO2 back-up switch (AT type only).

8.Check that the alarm lamp lights and the buzzer sound by pressing the alarm test key.

9.Make sure that liquid CO2 spouts into the chamber by pushing the CO2 back-up test switch.

10.Now you can put articles into the freezer chamber. Switch off the remote alarm switch and the CO2 back-up switch (AT type only) temporarily when putting in a lot of warm articles. Switch on these switches again after a certain period of operation.

Operation after power failure

The set value is memorized by nonvolatile memory in the event of power failure. Accordingly, the freezer resumes the operation with setting before power failure.

15

Image 16
Contents MDF-593 MDF-593AT MDF-793 MDF-793AT Contents Precautions for Safe Operation Symbol showsPrevent electric shock or injury Maintenance. These may be harmful to your health Water Precautions for Safe Operation Page Page Environmental Conditions Freezer Components Lock Control panel coverBreak down or power failure at the power supply Control panelInstallation Installation siteInstallation Adjust the leveling footRemove the packaging materials and tapes Fix the unitOperation after power failure START-UP of UnitRemote alarm terminal Temperature settingOperating Instructions Alarm temperature setting Setting of alarm resume time Alarm and safety functions Alarm and safety functionBack-up system Rough schemeFeeding of chart Temperature RecorderReplacement of cell Setting of back-up temperature PenholderRoutine Maintenance CleaningCleaning of condenser filter Defrosting of inside wallTrouble Shooting Disposal of Unit Recycle of NICKEL-CADMIUM Battery Location of a nickel-cadmium batteryRemoval of nickel-cadmium battery Handling of batterySpecifications PerformanceSafety check sheet 7FB6P10140500 25 Feb