TO CHANGE MAIN ORIFICE (Refer to Figure 2-36)

1.Turn off main gas supply valve.

2.Open 3/4" union in gas supply line.

3.Remove 1/2" nuts securing gas train to the burner housing.

4.Using a 11/16" wrench remove orifice from the mounting flange.

5.Install new orifice in reverse order.

WARNING

Before operating oven check for gas leaks!

TO CHANGE BYPASS (LOW FLAME) ORIFICE (Refer to

Figure 2-36)

1.Turn off main gas supply valve.

2.Open 3/4" union in gas supply line.

3.With 1/2" wrench loosen compression nuts securing bypass tube to solenoid valve.

4.Remove orifice from bypass tube.

5.Install new orifice in reverse order.

X. VOLUMETRIC METHOD

WARNING

Before operating oven check for gas leaks!

IMPORTANT

During these measurements, no other gas appliance should be in operation being supplied from the same gas meter.

To determine gas flow setting value “E”:

E= Liters/min.

NB

=

Rated input in kW

HuB

=

Heat (Calorific) value of gas in kW/m3

E= NB HuB

To determine the time of 0.1m3 (100 liters) gas usage:

Time in minutes =100

E

The time of the gas flow through the meter should be taken with a stopwatch.

1.Remove cover screw from the gas valve pressure (governor) adjustment valve.

2.Open main gas supply valve and start oven according to supplied instructions with the temperature control at maximum setting.

3.Once oven is in operation, adjust pressure valve (governor) to the calculated volume using the time for 100 liters of flow through. Turning the adjustment screw clockwise will increase the flow and counter-clockwise will reduce it.

2-28

Image 28
Contents Section Installation UNLOADING/UNPACKINGII. INSTALLATION, PREPARATION, and Supply Ventilation Hood Dimensions Recommendations onlyIII. Ventilation System RequirementsRecommendations Other Ventilation ConcernsInstallation KIT Dimensions and Data PS360L Tandem Dimensions and Data PS360WB Double Tandem Dimensions and Data PS360U Tri Tandem Dimensions and Data PS360WB-U Tri Tandem Dimensions and Data PS360U Quad Tandem Dimensions and Data PS360WB-U Quad Tandem Thermocouple Installation Locations IV. Thermocouple InstallationPlacing the Thermocouple Leads Thermocouple Lead Connections Assembly Exploded View Upper Oven StandCooling Fan Removal Oven Positioning and AlignmentJoining the Oven Bodies Aligning the Ovens for Assembly Bolts and SpacersChecking Track Rail Alignment Trim Strip PositioningTransition Frame Placement 22a Support Brackets Lower OvenInstalling the Transition Floor Panel Replacing Transition FrameInstalling the Conveyor Frame and Belt 25aInside Master Links Conveyor Link OrientationOutside Master Links Transition Assembly Conveyor Motor and Drive Chain AssemblyDo not USE Conduit For Ground GAS Supply Electrical SupplyOven Rough-In VI. Electrical Connection Typical Oven Data Plate Models PS360/PS360WB During Pressure Testing Note ONE Following Flexible Hose Connector InstallationVII. GAS Supply for GAS Heated Ovens For USE with Natural GAS VIII. Preparation for Various GasesFor USE with Liquid LP GAS Burner/Piping Assembly GAS Type and Pressure LabelVolumetric Method IX. Changing OrificesTo Check GAS Supply Pressure XI. Variations of Rated Supply PressuresOrifice Manifold Pressure Method Special Notices