CONTROL BOARD

FIG. 11-1 CONTROL BOARD

Location:

The Control Board is located inside the top cover behind the front face plate.

Test Procedures:

The test procedures for the control board will vary depending upon the problems experienced by the brewer. Refer to the Troubleshooting section which is divided into three sections, Refill Circuit, Heating Circuit, and Brewing Circuit.

Check for Power to board:

1.Insert one meter lead in J17-pin 9 and the other lead in J17-pin 11 (TR-2 to TR-5 ITB only).

2.With the power connected to brewer, the voltage reading to the board should be the line voltage rated for that model.

If no voltage is present, check wiring to the board. If voltage is present, and brewer does not power on, go to step 3

3.Check for line voltage at J15-1 BLK to J15-2 WHI (J14-1 to 2 ITB only)

If no voltage is present, replace the control board. If voltage is present, go to step 4

4.Check for 12VAC at J15-4 to J15-2 Yellow wires (J14-4 to J14-5 ITB only)

If no voltage is present, replace the trans- former. If voltage is present, and brewer does not power on, replace the control board.

Removal and Replacement:

1.Disconnect brewer from power source.

2.Disconnect the wires from the relay on the control board.

3.Disconnect all of the connectors from the control board.

4.Remove the two nuts securing the control board to the hood.

5.Tilt the control board inward to clear the display section.

6.Place the bottom edge of the new control board in the cradle, tilt the board forward, and secure with the two nuts to the hood.

7.Re-install connectors.

Faceplate Removal and Replacement:

1.Disconnect brewer from power source.

2.Disconnect the ribbon cable from the control board.

3.Models with faucet: Drain tank to below faucet outlet fitting. Remove hose, nut and washer from faucet. Remove faucet assembly.

4.Remove the four screws securing the face plate to the hood.

5.Carefully pull the ribbon cable through the front opening of the hood.

6.Installation is the reverse order.

FIG. 11-2 FACEPLATE REMOVAL

11

42461 0911809

 

Image 11
Contents ITB/ITCB ICB/TWIN BUNN-O-MATIC Commercial Product Warranty Introduction Control Boards TroubleshootingRemedy TroubleshootingRefill Circuit Problem Probable CauseHeating Circuit Problem Probable Cause Remedy Brewing Circuit Problem Probable Cause Remedy Problem Probable Cause Remedy Troubleshooting Brewing CircuitMessage Probable Cause Remedy DiagnosticsICB Component Access Component AccessControl Board Membrane Switch Continuity Membrane SwitchExploded View Early Brew ValveLate Model Brew Valve Brew Valve Late ModelsRefill Valves DisassemblyEarly Itcb Refill Valves Early ICBICB Twin Tank Heaters Tank HeatersLimit Thermostats Limit ThermostatTesting Temperature Probe Temperature ProbeCalibrate Temp Probe CalibrationTest Procedure Voltage Selector SwitchTest Procedure Removal and Replacement Power SwitchSchematic Wiring Diagram iTCBA, iTCBB Schematic Wiring Diagram With Factory Sweetener Schematic Wiring Diagram ICB-DV Schematic Wiring Diagram ICB Twin Schematic Wiring Diagram iCBA, iCBB Schematic Wiring Diagram ICB Twin 230V Chassis Ground Term Schematic Wiring Diagram ITB