2-20. HEATING ELEMENTS

10. Replace the brass nuts and washers on the heating element

(Continued)

 

terminals. Tighten the brass nuts to 30 foot lbs of torque.

 

11.

Replace heat contactor.

 

12.

Move the element spreaders from the center of the ele

 

 

ment, into a position which will spread each element apart

 

 

evenly on all four sides, and tighten.

 

13.

Replace the high limit bulb holder on the top element, and

 

 

position the bulb between the top and second element mid-

 

 

way from side to side, and tighten screw which holds the

 

 

bulb in place.

 

14.

Reconnect the wires to the appropriate terminal as labeled

 

 

when they were removed.

 

15.

Replace the front control shroud and control panel.

 

16.

Replace side panels.

 

17.

Connect the power cord to the wall receptacle or close

 

 

wall circuit breaker.

Heating elements should never be energized without shortening in the frypot, or damage to elements could result.

1103

2-21

Image 21
Contents Maintenance Hints MaintenanceIntroduction PreventiveCheckout High Temperature Fuse Holders Limit ControlReplacement Excess force will damage temperature probe Temperature Probe ReplacementYearly Inspection Every 90 daysUpright Reversing the LIDGasket Model 590/592 Pressure PAD Pressure pads are plastic strips that the lid cam pressesAgainst to seal the lid LID Adjustment Solenoid Valve If the core-disc assembly is sticking due to buildup Solenoid Valve Deadweight ValveRemoval & Cleaning Safety Relief Valve Deadweight ValveValve Cleaning StepsPressure Gauge Calibration Steps30 31 34 35 ContactorsIf either contactor proves defective, replace as follows Amperage Wires PowerHeating Elements Heating Elements 4 mm Gap Drain Valve Drain valve opens when the drain valve handle is pulledExtension Out and drains the shortening out of the potNylatron Strips Replacement Nylatron Strips Replacement