Hoshizaki KM-1300MWH, KM-1300MAH, KM-1300MRH Sanitizing Procedure Following Cleaning Procedure

Page 60

17) Close the Cleaning Valve.

Note: The icemaker will not operate unless the Cleaning Valve is completely closed.

18)Replace the Front Panel in its correct position.

19)Turn on the power supply to fill the Water Tank with water.

20)Turn off the power supply after 3 minutes.

21)Remove the Front Panel, and fully open the Cleaning Valve.

22)Move the Control Switch to the “Wash” position.

23)Replace the Front Panel in its correct position.

24)Turn on the power supply to rinse off the cleaning solution.

25)Turn off the power supply after 5 minutes.

26)Remove the Front Panel and Insulation Panel.

27)Drain the Water Tank. (See the above step 5.)

28)After the tank has drained, replace the removed parts in their correct positions.

Note: Do not replace the Insulation Panel when you proceed to “[b] SANITIZING PROCEDURE.’

29) Repeat the above steps 16) through 28) three more times to rinse thoroughly.

Note: If you do not sanitize the icemaker, go to step 9) in “[b] SANITIZING PROCEDURE.”

[b]SANITIZING PROCEDURE - Following Cleaning Procedure

1)Dilute a 5.25 % Sodium Hypochlorite solution (chlorine bleach) with water (Add 2.5 fl. oz. of sanitizer to 5 gal. of water).

2)Remove the Insulation Panel, if it is in its normal position.

3)Pour the sanitizing solution into the Water Tank.

60

Image 60
Contents KM-1300MAH KM-1300MWH KM-1300MRH Hoshizaki AMERICA, INC Contents Maintenance Specifications KM-1300MAH Air-cooled2a. KM-1300MWH Water-cooled 2b. KM-1300MWH Water-cooled Serial No. M10156D KM-1300MRH Remote air-cooled Condensing Unit URC-12F Specifications Model URC-12F II. General Information Construction KM-1300MWH Water-cooled KM-1300MRH Remote air-cooled Features of Control Products E Controller Board Controller BoardSOLID-STATE Control Controller BoardPage Beep every 3 sec. = High Evaporator Temperature 127 F Minute Fill CycleHarvest Cycle Freeze CycleControl Products HOS-001A Board Sequence 1st Cycle 2nd Cycle and after with pump drain 2nd Cycle and after with no pump drain Controls and Adjustments Setting Time Setting Frequency Checking the Controller Board Page III. Technical Information KM-1300MWH Water-cooled KM-1300MRH Remote air-cooled Wiring Diagrams KM-1300MAH Air-cooled and KM-1300MWH Water-cooledCut-out 412 ±21.3 Psig Cut-in 327±21.3 Psig Timing Chart Page Performance Data Serial # L00001F to M10155C KM-1300MWH Water-cooled Serial # M10156D KM-1300MRH Remote air-cooled IV. Service Diagnosis No ICE Production Problem Possible Cause RemedyController Board Problem Possible Cause Remedy Evaporator is Frozen UP LOW ICE ProductionAbnormal ICE OthersService for Refrigerant Lines Refrigerant RecoveryEvacuation and Recharge R-404A Brazing Removal and Replacement of Compressor Important Removal and Replacement of Drier Removal and Replacement of Expansion Valve Removal and Replacement of HOT GAS Valve and Line Valve Removal and Replacement of Evaporator Important Page Page Page Removal and Replacement of Thermistor Important Removal and Replacement of FAN Motor Removal and Replacement of Water Valve Removal and Replacement of Pump MotorRemoval and Replacement of Spray Tubes VI. Maintenance and Cleaning Instructions Preparing the Icemaker for Long StoragePage Cleaning Cleaning Procedure Sanitizing Procedure Following Cleaning Procedure Page Maintenance