Vermont Casting DVR28IN Below Grade Installations, Vertical Through-the-Roof Application

Page 14

Vermont Castings DVR28 Direct Vent Gas Fireplace

Below Grade Installations

When it is not possible to meet the required vent ter- minal clearances of 12” (305 mm) above grade level a snorkel kit is recommended. This allows installation depth of down to 7” (178 mm) below grade level. The 7” is measured from the center of the horizontal vent pipe as it penetrates through the wall.

Ensure the sidewall venting clearances are observed. If venting system is installed below ground, we recom- mend a window well with adequate and proper drainage to be installed around the termination.

If installing a snorkel, a minimum 24” (610 mm) vertical rise is necessary. The maximum horizontal run with the 24” vertical pipe is 36” (914 mm). This measurement is taken from the collar of the fireplace (or transition elbow) to the face of the exterior wall. See the Sidewall Venting Graph for extended horizontal run if the vertical exceeds 24” (610 mm).

1.Establish vent hole through the wall. (Fig. 17)

2.Remove soil to a depth of approximately 16”

(406 mm) below base of snorkel. Install window well (not supplied). Refill hole with 12” (305 mm) of coarse gravel leaving a clearance of approximately 4” (102 mm) below snorkel. (Fig. 23)

3.Install vent system. Refer to Page 12.

4.Ensure a watertight seal is made around the vent pipe coming through the wall.

5.Apply high temperature sealant caulking (supplied) around the 4” and 7” snorkel collars.

6.Slide the snorkel into the vent pipe and secure to the wall.

7.Level the soil to maintain a 4” (102 mm) clearance below snorkel. (Fig. 23)

Do not backfill around snorkel.

A clearance of at lest 4” must be main- tained between the snorkel and the soil.

If the foundation is recessed, use recess brackets (not supplied) for securing lower portion of the snorkel. Fas- ten brackets to wall first, then secure to snorkel with self drilling #8 x 1/2 sheet metal screws. It will be necessary to extend vent pipes out as far as the protruding wall face. (Fig. 24)

 

Snorkel

Foundation

 

Recess

 

 

Wall Screws

Watertight Seal

Sheet Metal

Around Pipe

Screws

BG401

Fig. 24 Snorkel installation, recessed foundation.

Vertical Through-the-Roof Application

This gas fireplace has been approved for:

Vertical installations up to 40’ (12 m) in height. Up to a 10’ (3 m) horizontal vent run can be installed within the vent system using a maximum of two 90° elbows. (Fig. 25)

Max. Height 40’

(12.2 m)Max. 10’ (3 m)

Zero Clearance Sleeve (if required)

Firestop

Screws 7TDVSNORK (Snorkel)

Min. Height 8’ (2.4 m)

7” Pipe

24” (610 mm )

Minimum *

4” Clear- ance Min.

Window

Well

Gravel

Drain

Foundation Wall

*A minimum of 24” (610 mm) vertical pipe must be installed when using the 7TDVSNORK.

Support Straps

Every 3’ (914 mm)

FP1757

Fig. 25 Support straps for horizontal runs.

Up to two 45° elbows may be used within the hori- zontal run. For each 45° elbow used on the horizon- tal plane, the maximum horizontal length must be reduced by 18” (450 mm).

Example: Maximum horizontal length:

BG404

Fig. 23 Below grade installation.

No elbows

=

10’ (3 m)

1 x 45° elbow

=

8.5’ (2.6 m)

2 x 45° elbows

=

7’ (2.1 m)

14

20012301

Image 14
Contents Direct Vent Model DVR28IN Table of Contents Ansi Z21.88-2005 / CSA Vented Gas Fireplace Heaters Installation & Operating InstructionsCertified To DVR28 Fireplace Dimensions Fireplace specifications and framing dimensionsMounting the Fireplace Installation Instructions PreparationLocating Your Fireplace Clearance to CombustiblesGas Inlet and Manifold Pressures Gas Line InstallationGas Specifications High ElevationsRestrictor Plate Installation InstallationGeneral Venting Location of Vent TerminationCanadian Installations1 US Installations2 General Venting Information Termination LocationGeneral Information Assembling Vent Pipes Canadian InstallationsUSA Installations Twist Lock PipesExample a How to Use the Vent GraphRear Wall Venting Applications Example BRear Wall Installation Twist Lock Pipe Zero clearance sleeve is only required for combustible wallsVertical Sidewall Applications Total angular variation =Below Grade Installations Vertical Through-the-Roof ApplicationVertical Through-the-Roof Installation Place firestop spacers and secureMinimum termination to roof clearance Venting Components Operating Instructions Window Frame Assembly RemovalGlass Cleaning Glass InformationInspecting the Venting System Flame & Temperature AdjustmentFlame Characteristics Lighting Instructions Lighting & Operating InstructionsFor Fireplaces equipped with AF4000 Gas Valve Turning Off the Gas to the ApplianceTroubleshooting AF4000 ValveTroubleshooting AF4000 Valve Igniter operationTroubleshooting AF4000 Valve Fireplace May Be HOT MaintenanceCleaning the Standing Pilot Control System Burner and Burner CompartmentDescription DVR28Screen Door Kit Optional AccessoriesCurve Face Kit Model # ColorLimited Lifetime Warranty Efficiency Ratings 67.6 64.3