Kohler Thermostatic Electric Shower manual Specifications, Installation Requirements, Plumbing

Page 8

Specifications

1. Plumbing

Minimum maintained inlet pressure 70 kPa (0.7 bar).

100 kPa (1.0 bar) recommended for satisfactory operation.

Maximum static inlet pressure 1000 kPa (10 bar).

Minimum static pressure 20 kPa (0.2 bar) to keep the inlet valve closed.

2. Electrical

The Mira Azora 9.8 kW requires a 45 Amp fuse.

The terminal block will accept cable up to 16 mm2 .

3. Standards and Approvals

The Mira Azora complies with all relevant directives for CE marking.

Installation Requirements

1. Plumbing

The appliance is designed to operate with a minimum maintained inlet pressure of 0.7 bar up to a maximum static inlet pressure of 10 bar. When installed in very hard water areas (above 200 ppm temporary hardness) your installer may advise the installation of a water treatment device, to reduce the effects of limescale formation. Your local water company will be able to advise the hardness of water in your area.

It is recommended that a non-restrictive (free flowing) isolating valve

is fitted in the cold water supply pipe to allow the complete maintenance of the appliance. Do not use a valve with a loose washer plate (jumper) as this can lead to a build up of static pressures.

The appliance is suitable for installation within the shower area. It is fitted

with a pressure relief device and must be positioned over a water catchment area with the controls at a convenient height for all users.

The appliance must be fitted on to a finished flat and even wall surface

(this wall surface should be tiled or waterproofed). Do not fit the appliance to the wall and tile up to the case. For safety requirements, an air gap must be left behind the appliance.

Image 8
Contents These instructions are to be left with the user Contents Introduction Mira Azora 9.8 kWImportant Safety Information Page Pack Contents Checklist DocumentationMira Energise Electric Shower Fittings Specifications Installation RequirementsPlumbing ElectricalShower Tray Electrical Installation Installation of Mira Azora Page = Brown = GREEN/YELLOW N = Blue Page Installation of Shower Fittings End Support Slidebar End Commissioning 10.1113.14 17.18Read the section Important Safety Information first User InstructionsSpray Action EcoFault Diagnosis Only a Competent Tradesperson should Remove the Front CoverHigh Low or No Maintenance Handset CleaningInlet Filter Cleaning/Renewing Read the section Important Safety Information firstSpare Parts List Mira Azora Spare Parts List AccessoriesMira Azora Spare Parts Diagram Mira Energise Shower Fittings Spare Parts List Dimensions Wiring Diagram Internal Wiring DiagramCustomer Services Mira Showers