Generac Power Systems 04389-1, 04456-1, 04390-1 owner manual Generator Tests Under Load

Page 13

Section 2 — Post Installation Start-up and Adjustments

Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators

10.Connect an accurate AC voltmeter and a frequen- cy meter across transfer switch terminal lugs E1 and E2. Voltage should be 242-252 volts; fre- quency should read about 61-63 Hertz.

11.Connect the AC voltmeter test leads across termi- nal lug E1 and neutral; then across E2 and neu- tral. In both cases, voltage reading should be 121- 126 volts AC.

12.Set the generator’s main circuit breaker to its OFF (or open) position. Let the engine run at no- load for a few minutes to stabilize internal engine generator temperatures.

13.Set the generator's Auto/Off/Manual switch to OFF. The engine should shut down.

NOTE:

It is important not to proceed until you are certain that generator AC voltage and frequency are cor- rect and within the stated limits. Generally, if both AC frequency and voltage are high or low, the engine governor requires adjustment. If frequency is correct, but voltage is high or low, the genera- tor’s voltage regulator requires adjustment.

2.4GENERATOR TESTS UNDER LOAD

To test the generator set with electrical loads applied, proceed as follows:

1.Set generator’s main circuit breaker to its OFF (or open) position.

2.Turn OFF all loads connected to the transfer switch terminals T1 and T2.

3.Set the generator's Auto/Off/Manual switch to OFF.

4.Turn OFF the utility power supply to the transfer switch, using the means provided (such as a util- ity main line circuit breaker).

Do not attempt manual transfer switch opera- tion until all power voltage supplies to the transfer switch have been positively turned off. Failure to turn off all power voltage supplies will result in extremely hazardous and possibly fatal electrical shock.

5.Manually set the transfer switch to the STANDBY position, i.e., load terminals connected to the generator's E1/E2 terminals. The transfer switch operating lever should be down.

6.Set the generator's Auto/Off/Manual switch to MANUAL. The engine should crank and start immediately.

7.Let the engine stabilize and warm up for a few minutes.

8.Set the generator’s main circuit breaker to its ON (or closed) position. Loads are now powered by the standby generator.

9.Turn ON electrical loads connected to transfer switch T1 and T2. Apply an electrical load equal to the full rated wattage/amperage capacity of the installed generator.

10.Connect an accurate AC voltmeter and a frequen- cy meter across terminal lugs E1 and E2. Voltage should be greater than 230 volts; frequency should be greater than 58 Hertz.

11.Let the generator run at full rated load for 20-30 minutes. Listen for unusual noises, vibration or other indications of abnormal operation. Check for oil leaks, evidence of overheating, etc.

12.When testing under load is complete, turn OFF electrical loads.

13.Set the generator's main circuit breaker to its OFF (or open) position.

14.Let the engine run at no-load for a few minutes.

15.Set the Auto/Off/Manual switch to OFF. The engine should shut down.

2.5CHECKING AUTOMATIC

OPERATION

To check the system for proper automatic operation, proceed as follows:

1.Set generator’s main circuit breaker to its OFF (or open) position.

2.Check that the Auto/Off/Manual switch is set to OFF.

3.Turn OFF the utility power supply to the transfer switch, using means provided (such as a utility main line circuit breaker).

4.Manually set the transfer switch to the UTILITY position, i.e., load terminals connected to the util- ity power source side.

5.Turn ON the utility power supply to the transfer switch, using the means provided (such as a util- ity main line circuit breaker).

6.Set the Auto/Off/Manual switch to AUTO. The sys- tem is now ready for automatic operation.

7.Turn OFF the utility power supply to the transfer switch.

With the Auto/Off/Manual switch at AUTO, the engine should crank and start when the utility source power is turned OFF. After starting, the transfer switch should connect load circuits to the standby side. Let the system go through its entire automatic sequence of operation.

With the generator running and loads powered by generator AC output, turn ON the utility power sup- ply to the transfer switch. The following should occur:

After about six seconds, the switch should transfer loads back to the utility power source.

About one minute after retransfer, the engine should shut down.

Generac® Power Systems, Inc. 11

Image 13
Contents Installation Authorized Dealer Location IntroductionMaintenance Post Installation Start-up AdjustmentsTroubleshooting Introduction Inside Front CoverGeneral Hazards ‹ Standards Index Electrical HazardsProtection Systems UNPACKING/INSPECTIONSystem SET LED 7 kW, Single Cylinder GH-410 Engine Your Generator‹ 1.5.1 Generator Specifications‹ 1.5.2 Engine Fuel Requirements Recommendations Reconfiguring the Fuel SystemFuel Consumption 1 7 KW, 410CC EngineLocation Transfer SwitchGenerator 2.1 7 kW, 12 kW and 15 kW UnitsBattery Battery InstallationBefore Initial START-UP Check Transfer Switch OperationElectrical Checks Checking Automatic Operation Generator Tests Under LoadEngine Governor Adjustment Adjusting the Regulator Natural GAS only1 7 KW Units 2 12 KW and 15 KW Units Voltage Regulator AdjustmentAutomatic Transfer Operation BREAK-IN Procedure‹ 3.2.3 Manual Position ‹ 3.2.1 Auto PositionManual Transfer Operation Sequence of Automatic Operation‹ 3.5.2 Transfer Back to Utility Power Source Setting the Exercise Timer‹ 3.7.1 LOW OIL Pressure Switch ‹ 3.7.2 High Temperature SwitchApproximate Crank Cycle Times Checking the Engine OIL Level‹ 3.7.4 Overspeed Changing the Engine OIL ‹ 4.3.2 OIL Change ProcedureChanging the OIL Filter ‹ 4.3.1 Engine OIL RecommendationsSpark Plugs Battery MaintenanceCooling System Adjusting GH-410/GT-990 Valve Clearance‹ 4.12.1 Removal from Service OUT of Service Procedure‹ 4.12.2 Return to Service Corrosion ProtectionSYSTEM/COMPONENT Procedure Frequency Service ScheduleProblem Cause Correction Troubleshooting GuideElectrical Data Customer Battery Utility Battery Charger Utility Connection BCR Customer Connections Neutral Exploded Views and Parts Lists Part NO.QTY. Description Exploded Views and Parts Lists QTY Description Exploded Views and Parts Lists BOX GTS Load Center Exploded Views and Parts Lists COVER, 12 Position GTS Load Center Kit Contains BUSHING, Governor Lower 138 122 KNOB, AIR Cleaner 28 31 ADAPTOR, Engine Exploded Views and Parts Lists Stator 12KW Exploded Views and Parts Lists ASSEMBLY, Connecting ROD Exploded Views and Parts Lists SCREW, Taptite M6-1.0X8 Yellow Chrome Engine only Mounting Dimensions Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators MANUFACTURER’S Emission Control System Warranty Coverage Your Warranty Rights and ObligationsPURCHASER’S/OWNER’S Warranty Responsibilities Emission Related Parts Include the Following Emission Control System WarrantyThis Warranty Shall not Apply to the Following Warranty Schedule