Generac Power Systems 04389-1, 04456-1, 04390-1 BREAK-IN Procedure, Automatic Transfer Operation

Page 16

Section 3 — Operation

Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators

3.1 BREAK-IN PROCEDURE

‹ 3.2.3 “MANUAL” POSITION

Once the unit has been installed and all electrical checks have been made, it is strongly recommended that the following “Break-in Procedure” be completed to ensure correct generator operation in the future.

1. Set the generator’s Auto/Off/Manual switch to

AUTO.

Set the switch to Manual to crank and start the engine. Transfer to standby power will not occur unless there is a utility failure.

Figure 3.1 – Generator Control Panel

2.

Turn OFF the utility power supply to the transfer

 

switch using the means provided (such as a utili-

 

ty main line circuit breaker).

3.

The unit will start, and the transfer switch will

 

transfer to standby.

4.

Using the transfer switch’s built-in emergency

 

load center, turn on circuits to load the generator

 

to approximately 25% rated load and run the unit

 

for one hour.

5.

Run the unit for one hour at 50% rated load.

6.

Run the unit for one hour at 75% rated load.

7.

Run the unit for one hour at 100% rated load.

FUSE

 

5A

OFF MAN.

AUTO

FUSE

 

15A

SET

 

EXERCISE

 

TIME

L o c a t e y o u r n e a r e s t d e a le r a t :

POWER SYSTEMS, INC.

SYSTEM SET

LOW OIL

HIGH TEMP.

OVER SPEED

OVER CRANK

F L A S H IN G G R E E N L E D =

N O U T IL IT Y S E N S E 4 F L A S H IN G R E D L E D S =

E X E R C IS E R N O T S E T

8.

Turn ON the utility power supply to the transfer

 

switch, which will allow the transfer switch to

 

transfer back to utility power. The unit will con-

 

tinue to run for one minute and then shut down.

9.

Allow the unit to cool.

10.

Set the generator's Auto/Off/Manual switch to

 

OFF. Remove the 5A and 15A fuses from the gen-

 

erator control panel. Disconnect the battery

 

cables as outlined in “General Hazards” (page 2).

11.

Drain the oil and remove the oil filter. Replace the

 

oil filter according to Section 4.4, “Changing the

 

Oil Filter”. Replace the oil with synthetic oil as

 

recommended in Section 4.3, “Changing the

 

Engine Oil”.

12.

Reconnect the battery cables as outlined in

 

“General Hazards” (page 2) and insert the 5A and

 

15A fuses into the generator control panel. The

 

generator is now ready for service.

3.2USING THE AUTO/OFF/MANUAL SWITCH (FIGURE 3.1)

‹3.2.1 “AUTO” POSITION

Selecting this switch position activates fully automat- ic system operation. It also allows personnel to start and exercise the engine every seven days with the set- ting of the exercise timer (see Section 3.6). This posi- tion also is used for remote starting, when it is set up.

‹3.2.2 “OFF” POSITION

This switch position shuts down the engine. This position also prevents automatic operation.

With the switch set to AUTO, the engine may

!crank and start at any time without warning. Such automatic starting normally occurs when utility power source voltage drops below a pre- set level or during the normal exercise cycle. To prevent possible injury that might be caused by such sudden starts, always set the switch to OFF and remove the fuses before working on or around the generator or transfer switch. Then, place a “DO NOT OPERATE” tag on the generator panel and on the transfer switch.

3.3AUTOMATIC TRANSFER

OPERATION

To select automatic operation, do the following:

1.Make sure the transfer switch main contacts are set to their “Utility” position, i.e., loads connected to the utility power source (Figure 3.2).

2.Be sure that normal utility power source voltage is available to transfer switch terminal lugs N1 and N2.

3.Set the generator’s Auto/Off/Manual switch to AUTO.

4.Set the generator’s main circuit breaker to its ON (or closed) position.

With the preceding steps complete, the generator will start automatically when utility source voltage drops below a preset level. After the unit starts, loads are transferred to the standby power source. Refer to Section 3.4, “Sequence of Automatic Operation.”

14 Generac® Power Systems, Inc.

Image 16
Contents Installation Introduction Authorized Dealer LocationPost Installation Start-up Adjustments MaintenanceTroubleshooting Introduction Inside Front CoverGeneral Hazards Electrical Hazards ‹ Standards IndexProtection Systems UNPACKING/INSPECTIONSystem SET LED Your Generator 7 kW, Single Cylinder GH-410 Engine‹ 1.5.1 Generator Specifications‹ 1.5.2 Engine Reconfiguring the Fuel System Fuel Requirements RecommendationsFuel Consumption 1 7 KW, 410CC EngineTransfer Switch LocationGenerator 2.1 7 kW, 12 kW and 15 kW UnitsBattery Installation BatteryBefore Initial START-UP Check Transfer Switch OperationElectrical Checks Generator Tests Under Load Checking Automatic OperationEngine Governor Adjustment Adjusting the Regulator Natural GAS only1 7 KW Units Voltage Regulator Adjustment 2 12 KW and 15 KW UnitsBREAK-IN Procedure Automatic Transfer Operation‹ 3.2.3 Manual Position ‹ 3.2.1 Auto PositionSequence of Automatic Operation Manual Transfer OperationSetting the Exercise Timer ‹ 3.5.2 Transfer Back to Utility Power Source‹ 3.7.1 LOW OIL Pressure Switch ‹ 3.7.2 High Temperature SwitchApproximate Crank Cycle Times Checking the Engine OIL Level‹ 3.7.4 Overspeed ‹ 4.3.2 OIL Change Procedure Changing the Engine OILChanging the OIL Filter ‹ 4.3.1 Engine OIL RecommendationsBattery Maintenance Spark PlugsAdjusting GH-410/GT-990 Valve Clearance Cooling SystemOUT of Service Procedure ‹ 4.12.1 Removal from Service‹ 4.12.2 Return to Service Corrosion ProtectionService Schedule SYSTEM/COMPONENT Procedure FrequencyTroubleshooting Guide Problem Cause CorrectionElectrical Data Customer Battery Utility Battery Charger Utility Connection BCR Customer Connections Neutral Exploded Views and Parts Lists Part NO.QTY. Description Exploded Views and Parts Lists QTY Description Exploded Views and Parts Lists BOX GTS Load Center Exploded Views and Parts Lists COVER, 12 Position GTS Load Center Kit Contains BUSHING, Governor Lower 138 122 KNOB, AIR Cleaner 28 31 ADAPTOR, Engine Exploded Views and Parts Lists Stator 12KW Exploded Views and Parts Lists ASSEMBLY, Connecting ROD Exploded Views and Parts Lists SCREW, Taptite M6-1.0X8 Yellow Chrome Engine only Mounting Dimensions Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators MANUFACTURER’S Emission Control System Warranty Coverage Your Warranty Rights and ObligationsPURCHASER’S/OWNER’S Warranty Responsibilities Emission Control System Warranty Emission Related Parts Include the FollowingWarranty Schedule This Warranty Shall not Apply to the Following