11Symmetra MW II 1200 kW 3 x 400/230 V Installation - 990-1979E-001
Top cable entry
1. Loosen the 8 bolts to remove top cover.
Note: No drilling or cutting should take place over the top of the UPS.
2. Drill holes for grommets.
3. Re-fit the covers and install the grommets.
4. Feed the cables through the grommets. Connect cables at cable connection points.
5. Connect Protective Earth conductor to busbar locations.
~~NormalUPS SummaryNormalX022
X021
X007
X010
X011
X008B
X008A
X012
X013
X014A
X014B
X017
X405 L1 IN L2 IN L3 IN L1 OUT L2 OUT L3 OUTL3 INL3 OUTL2 INL2 OUTL1 INL1 OUT