SECTION 15950
CONTROLS
[Note to Consultant: These standards incorporate the suggested wording for contract specifications. The consultant is responsible for making sure that the specifications are edited to meet the scope and intent of the project. Items which specifically require editing are highlighted in bold and enclosed in brackets.]
PART 1 - GENERAL
1.01RELATED WORK SPECIFIED ELSEWHERE General Requirements Divisions 0 and 1
Mechanical Division 15
Testing, Balancing, and Adjusting Section 15990
Electrical Division 16
[Note to Consultant: Include Commissioning here if used.]
A.The General Conditions of the Contract, Supplementary Conditions, and General Require- ments bound herewith are a part of these Specifications and shall be used in conjunction with this Division as a part of the Contract Documents. Consult them for further instructions pertaining to this work. Contractors shall be responsible for, and be governed
by, all requirements thereunder.
B. Electrical wiring in connection with the automatic temperature control system, where
shown on the Division 16 drawings, shall be performed by the Electrical Contractor. All other wiring required for proper operation of the automatic temperature system shall be performed by this Contractor.
C.The automatic temperature control valves, separable wells for immersion sensors, and taps for flow and pressure instruments shall be provided by the Controls Contractor for
installation by the Mechanical Contractor under the Controls Contractor's supervision.
D.All automatic temperature control dampers shall be provided by the Controls Contractor for installation by the Mechanical Contractor under the Control Contractor's supervision, unless
they are components of packaged equipment.
[Note to Consultant:
E. Adjustments of manual balancing devices, as required to obtain design air and/or water
JANUARY 2008 | UCCS STANDARDS |