F. This Contractor shall demonstrate HVAC alarms prior to placing ventilation systems in service.
G.The control systems will not be accepted as meeting the Requirements of Completion until all tests described in this section have been performed to the satisfaction of both the Engi- neer and Owner. Any tests that cannot be performed due to circumstances beyond the
control of the Contractor may be exempt from the Completion Requirements if stated as such in writing by the Owner's representative. Such tests shall then be performed as part of the warranty.
H.After the system has operated properly for 90 days following startup of the final component of the heating and air conditioning systems,
approve. The Contractor shall immediately provide updated copies of the files.
3.12CONTROL EXECUTION - GENERAL
A. This Contractor shall provide all required control interface relays, including Control Contactors for
wiring to
B.This Contractor shall be responsible for providing control power to all his controllers and devices requiring control power including installation of any required breakers, unless such
wiring is shown on the Division 16 drawings.
C.Accessibility: Install all control devices in readily accessible locations as defined by Chapter 1, Article 100, Part A of the NEC.
D.Program as follows: Initially set times so as not to exceed six starts per hour. On two- speed motors, provide a
E. All setpoints, operating points, sequencing ratios, PID tuning parameters, and all other numeric and digital constants shall be adjustable by the user (only with a