j. Each miscellaneous monitored or controlled point

2.Menu Penetrations: “Buttons” shall be provided to allow the user to easily move among the various graphics and menus. At any time, the operator shall be able to return to the main menu with one mouse click and shall switch from graphic to other modes within two mouse clicks.

C.Alarm Setup:

1.UCCS personnel shall program all general equipment alarms not specified elsewhere in this section. Alarm programming will begin after the contractor has completed programming for all controllers and the new control system is on-line on the campus Delta network..

2.The contractor shall allow full access to the control system by authorized UCCS per- sonnel for the purpose of programming alarms.

D.Trend Logging:

1.The system shall trend and display numerically and graphically any analog or digital points in the system.

2.Trend logging and historical logging shall be programmed for all points and be fully operational.

3.14FIBER OPTICS - NETWORKING [Note to Consultant: The networking requirement varies for each job. This section will have to be modified for each project involving Delta Controls. The requirements for a given project will be provided by the UCCS Delta Controls System Administrator upon request.]

A.Provide all required translators and power connections required to connect DDC panels to the University network. Fiber will be routed from the main telephone closet in the [Add building name] Building, Room # [______], to the enclosure in the mechanical room where the Infilink will be mounted, Room # [______]. The conduit and fiber will be provided under separate contract.

B.The fiber network is duplex multi-mode A and D (two strands of fiber). At least one spare set of fiber strands is included with each run.

C.Power is already provided at the [Add

building name] Building location. The UCCS Telecommunications Department will make all necessary connections in the campus fiber network to make a continuous run from the [Add building name] Building to the [Add building name] Building.

D.The temperature controls contractor shall be responsible for connecting the new Infilink in the [Add building name] Building to the other Infilinks already mounted at that location. Final connection of the [Add building name] Building controls to the campus Delta Network, and bringing them on-line, shall be supervised by and be the responsibility of the

JANUARY 2008

UCCS STANDARDS

15950-41

Page 41
Image 41
APC UCCS Temperature Control specifications 15950-41