information.
6.When connecting DDC controllers, terminating of inputs and outputs shall be color coded as follows :
120VAC shall be black = hot, white = neutral, green = ground 24VAC shall be (+) black with white tracer,
All pneumatic tubing shall be labeled within 2" of termination with a descriptive identifier.
7.All metal and plastic engraved labels shall be secured with chains, nylon
8.All switches, relays, and panel components shall be labeled.
9.Labels shall not be mounted on removable surfaces, such as cable tray covers.
3.09PROTECTION
A.The Contractor shall protect all work and material from damage by his work or workmen, and shall be liable for all damage thus caused.
B.The Contractor shall be responsible for work and equipment until finally inspected, tested, and accepted. He shall protect work against theft, injury, or damage; and shall carefully store material and equipment received on site which is not immediately installed. He shall close open ends of work with temporary covers or plugs during storage and construction to prevent entry of foreign objects.
3.10 CLEANUP
A.At the completion of work, all equipment on the project shall be checked and thoroughly cleaned including under equipment and any and all other areas around or in equipment provided under this section. Clean exposed surfaces of all equipment and panels of all grease, plaster, or other foreign material. Remove all
B.At the completion of the work, remove from the building, the premises, and surrounding streets, alleys, etc., all rubbish and debris resulting from this project, and leave all equipment spaces clean and ready for use.
C.At the completion of work, all equipment furnished under this contract shall be checked for paint damage, and any factory finished paint that has been damaged shall be repaired to match the adjacent areas. Any metal cabinet, jacket, or enclosure that has been deformed shall be replaced with new material and repainted to match the adjacent areas.
3.11TESTING
A.Prior to substantial completion, the control system shall undergo a series of tests to verify operation and compliance with this specification. These tests shall occur after the Con-
tractor has completed the installation, started up the system, and performed his own per-