and approval.
D. Coordination: This Contractor shall interface with controls furnished with equipment. Provide additional control devices, interlock relays, and signal conditioners when necessary to accomplish specified sequences.
E.The system shall include all interlocks, field devices, wiring, piping, hardware, and software required to provide a complete, functional system in accordance with these specifications and drawings.
F.The distribution of points and the type of controllers shown on the control panels depicted on the Contract Documents show the actual layout to be used by the Contractor when bidding and installing the controls. It is the Contractor’s responsibility to include in his bid the cost of any additional controllers necessary for a complete job, conforming to specifications.
G. If pneumatic controls are to be used, the Controls Contractor shall coordinate with the Fire Alarm Contractor to connect the air supply to all pneumatic controls for fire/smoke dampers and
1.04WORK INCLUDED
A.Furnishing and installing a complete, fully functional control system per this specification and the Construction Documents (drawings, specifications, addenda, etc.).
B.
C.Actuators, thermostats, sensors, transmitters, thermowells, instrument air compressors, filter/dryers, gauges, and mounting hardware as applicable.
D.Control valves, dampers, linkages, and mounting hardware.
E.Construction supervision.
F.Startup and performance testing.
G.Demonstration and training.
H.Warranty.
I. Demolition:
When equipment wiring, piping, pneumatics, tubing, telecommunications, cables etc. are abandoned or disconnected, they must be physically removed and disposed of in a professional manner. In cases where the demo could have an adverse effect, or where the