commissioning

First ignition operation

Date . . . . . . . . . . . .

Installer . . . . . . . . . .

1.Check the electrical supply.

Complete . . . . . .

6.Measure the gas inlet pressure. standing + warming pressure

Complete . . . . . .

7.Check the hydraulic water tightness.

Complete . . . . . .

10.Set up heating controls Complete . . . . . .

13.Adjust DHW flow rate on the boiler (if necessary).

Complete . . . . . .

2.Check the type of gas and change the gas if necessary.

Complete . . . . . .

5.Check the exhaust flue. See page 18

Complete . . . . . .

8.Spin the pump.

Complete . . . . . .

11.Balance the central heating circuit.

Complete . . . . . .

14.Analyse the combustion (see page 33)

Complete . . . . . .

3.Check the gas tightness.

Complete . . . . . .

6.Fill the installation.

See page 30

Complete . . . . . .

9.Set the heating power. See page 31

Complete . . . . . .

12.Check the boiler in DHW mode (combi only)

Complete . . . . . .

15.Check the ionisation current.

Complete . . . . . .

16.Explain to the end user the the boiler operation.

Complete . . . . . .

17.At the time of commissioning, complete all relevant sections of the Benchmark Checklist located on the inside back pages of this document.

Complete . . . . . .

29

Page 29
Image 29