Figure D

RAMP OPERATION

Ramp Manual Operation (continued)

To Reengage Carriage Assembly to Drive Chain:

1.

Position the ramp platform

4.

Grasp the platform Hand Hold

6.

Verify mechanism is reen-

 

manually so that only 15 cm

 

and move the platform slightly

 

gaged (locked). Pull on the

 

is extended out of the cas-

 

outward until platform locks

 

Hand Hold to ensure no

2.

sette.

 

into position (secured by re-

7.

movement occurs.

Turn (loosen) the manual

 

engaging the carriage assem-

Stow the remaining portion

3.

release “T” handle 90°.

5.

bly with the drive chain).

 

of the platform by using the

Push the “T” handle fully

Turn (tighten) the “T” handle

 

electrical system.

 

inward until handle contacts

 

90° to secure handle in the

 

 

 

shaft shoulder (3" to 4").

 

engaged (locked) position.

 

 

Figure D Figure EManual background

TURN

TURN

 

 

TURN

 

 

TO

TO

 

LOCK

TO

LOCK

 

 

 

LOCK

Step 2

Step 3

Step 5

Figure E