!CAUTION
UNIT DAMAGE HAZARD
Failure to follow this caution may result in component damage.
DO NOT redrill orifices. Improper drilling (burrs,
h.Jumper R to W/W1.
i.Let furnace run for 3 minutes in
j.Measure time (in sec) for gas meter to complete 1 revolution. Note reading.
k.Refer to Table 12 for cubic ft of gas per hr.
l.Multiply gas rate cu ft/hr by heating value (Btu/cu ft).
m.Move setup switch
EXAMPLE:
Btuh heating input = Btuh/cu ft X cu ft/hr Heating value of gas = 975 Btuh/cu ft Time for 1 revolution of
Btuh heating input = 103 X 975 = 79,950 Btuh
In this example, the orifice size and manifold pressure adjustment is within +/- 2 percent of the furnace input rate.
n. Remove jumper across R, W/W1, and W2 thermostat connections to terminate call for heat.
ALTITUDE | % OF | DERATE MULTIPLIER |
(FT) | DERATE | FACTOR FOR U.S.A.* |
0 | 1.00 | |
0.95 | ||
0.93 | ||
0.91 | ||
0.89 | ||
0.87 | ||
0.85 | ||
0.83 | ||
0.81 |
*Derate multiplier factor is based on midpoint altitude for altitude range.
Table 11 – Altitude Derate Multiplier for U.S.A.
o.Wait for blower
p.Jumper R and W/W1 thermostat connections on control to start furnace.
q.Wait for the blower to turn ON then repeat items i through l for
NOTE: Measured gas inputs (high heat, medium heat, and low heat) must be within
BURNER FLAME
BURNER
MANIFOLD
A89020
Fig. 62 - Burner Flame
355CAV
57