Venting and Combustion Air Installation

Category IV Vent Termination Clearances

Maintain the following clearances to the vent termination:

-At least 6 feet from adjacent walls

-No closer than 5 feet below roof over- hangs

-At least 7 feet above any public walk- ways

-At least 3 feet above any forced air intake (does not include the combustion air inlet) within 10 feet.

-The vent termination must be at least 4 feet from any electric meters, gas meter-regulators, relief valves or other equipment. Never terminate the vent above or below any of these items with- in 4 feet.

-Vent must terminate at least 12 inches above grade or common snow line.

NOTICE

In those applications in which the vent termination is below the projected snow line. The installer has 2 options. In the first option the vent system can be rout- ed vertically through an insulated chase or “riser box” and then terminated hori- zontally. The chase is to be constructed and insulated by the contractor, main- taining clearances for vertical and hori- zontal enclosures. In the second option the installer can use the horizontal con- centric snorket kit, see Fig. 22B page 34.

If the venting application is a horizontal direct vent:

-Must maintain 12-inch clearances below and horizontally from doors and windows. See dimension A Fig. 17.

If the venting application is a horizontal non-direct vent:

Dimension A

Direct Vent - 12 inches

Non-Direct Vent - 4 feet

Fig.17: Termination of Vent system

28

Page 34
Image 34
Delta PG PLUS-25 warranty Venting and Combustion Air Installation, Category IV Vent Termination Clearances