STEP 1: MOUNT THE TRANSMITTER

Quick Installation Guide

Rosemount 3095 MultiVariable

00825-0100-4716, Rev DA October 2009

STEP 1: MOUNT THE TRANSMITTER

Liquid Flow Applications

1. Place taps to the side of the line.

2. Mount beside or below the taps.

3. Mount the transmitter so that the drain/vent valves are oriented upward.

Liquid Flow Applications Flow

Gas Flow Applications

1. Place taps in the top or side of the line.

2. Mount beside or above the taps.

Gas Flow Applications Flow

Steam Flow ApplicationsManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background Flow

Steam Flow Applications

1.

Place taps to the side of the line.

 

2.

Mount beside or below the taps.

 

3.

Fill impulse lines with water.

Flow

 

 

Figure 1. Using a Mounting Bracket

 

Panel Mount(1)

Pipe Mount

(1)Panel bolts are customer supplied.