Installation

ORCA-IV Image Transfer Laminator Operation Manual

 

 

Figure 2-8: Leveling Side to Side

6.Place the level directly on the chrome tie bar in the front of the machine and level the front of the machine side to side.

7.Recheck the front to rear level condition to ensure that it has not changed. If it has, repeat the leveling procedure.

8.Remove the four metal casters after the machine is leveled (casters provided for transportation only).

6WDUWXS

The first time the image transfer laminator is started and every time it is serviced you should use the following checklist to confirm that the unit is operating properly and that all safety mechanisms are functioning.

Startup Checklist

Start the image transfer laminator and go through the following checklist.

Are the emergency stop buttons working?

Push down on one of the emergency stop buttons. The image transfer laminator should stop immedi- ately. Reset the button by turning it clockwise until it pops up. Press the reset button. See Figure 1-4:

Machine Reset Button to locate the main machine reset button. Start the laminator. The machine should resume operation. Always check all four buttons.

IMPORTANT

Never operate the image transfer laminator unless all of the emergency stop buttons are functioning properly. You can be crushed or burned.

Are the emergency stop kick cables working? With the laminator running, step on or kick the front emergency stop kick cable. The rolls should stop turning and rise, if they are lowered. Reset the kick cable button. See Figure 1-3: Kick Cable Reset Button to locate the kick cable reset button. Then reset the main machine reset. See Figure 1-4: Machine Reset Button to locate the main machine reset button.

IMPORTANT

Never operate the image transfer laminator unless both of the emergency stop kick cables are functioning properly. You can be crushed or burned.

2-6

© GBC Pro-Tech 1998 October