Installation Instructions
WALL PLENUM AND ARCHITECTURAL LOUVER INSTALLATION
•Install the appropriate wall plenum through the exterior wall in accordance with the Installation Instructions provided with the plenum.
IMPORTANT: The wall plenum is not designed to carry structural loads. Proper wall header construction is required. The plenum requires proper flashing, shim and caulk for a weather resistant installation.
Proper header for structural support. Apply proper caulking and flashing.
Properly square and level plenum.
Architectural
Exterior/Outside Wall
Wall Plenum |
| |
RAVWP6 – 6”D x 193⁄4”W x 32”H |
| |
RAVWP8 – 8”D x 193⁄4”W x 32”H |
| |
RAVWP12 – 12”D x 193⁄4”W x 32”H | Case | |
RAVWP15 – 15”D x 193⁄4”W x 32”H | ||
|
1BUILD AND INSTALL THE ZONELINE BASE PLATFORM
1.Construct a 231⁄4” min. x 231⁄4” min. square platform with legs to raise the platform a minimum of 8”.
NOTE: The platform must have a
2. Make drain hole cutout(s): |
• Primary Drain – Centerline of drain is |
approximately 51⁄4” from left platform edge |
and 81⁄2” from back platform edge. |
• Secondary Drain – Centerline of drain |
is approximately 61⁄2” from left platform edge |
and 51⁄4” from back platform edge. |
Left side of platform 231⁄4” min.
8”min.
for drain access
NOTE: Specific cutout size for drain connections needs
to be determined by the installer for the given installation situation.
Back of platform 231⁄4” min.
Cutout for drain
51⁄4” connection(s) (see NOTE below)
51⁄4” 61⁄2” 81⁄2”
3. Place the platform in the utility closet |
with the following clearance between it |
and the interior surface of the walls/door/panel: |
• 4” min. from front of the case – |
Unit to be installed through FRONT of case |
• 5” min. from front of the case – |
Unit to be installed through SIDE of case |
• 3” min. from two sides of the case (5” for side |
installation). |
4. Align the platform with the opening of |
the wall plenum and secure to the floor |
using appropriate brackets and bolts. |
18