GE AZ75H18EAC, 49-7419-2 8FINAL CHECK, 9CONNECT POWER, Servicing, Installation Instructions

Models: 49-7419-2 AZ75H18EAC

1 28
Download 28 pages 41.01 Kb
Page 22
Image 22
8FINAL CHECK

Installation Instructions

8FINAL CHECK

Review this Checklist before restoring power.

Correct line voltage?

Single circuit only?

HVACR type breaker/fuse?

Ductwork connected?

Case and unit level?

Wall plenum caulked? Level? Flashing?

Drain connected?

Wall thermostat wired correctly?

Unit wired correctly?

9CONNECT POWER

1.If all the above items are correct, turn the power on at the main service panel.

2.Turn the unit power switch, on the front of the unit, to ON by pressing the top of the switch in.

SERVICING

9CONNECT POWERWARNING: Before servicing, switch power off at the service panel and lock the area to prevent power from being switched on accidentally. When the area cannot be locked, securely fasten a prominent warning device, such as a tag, to the service panel.

NOTE: We strongly recommend that any servicing be performed by a qualified individual.

For ease of service, the unit can be removed from the case:

1.Unplug the power cord and disconnect the wall thermostat connections.

2.Raise the top duct by turning all four case top duct adjusting screws counterclockwise.

3.Remove the front case panel.

4.Remove the front and/or side case-to-unit grounding screw, if present.

5.Slide the unit out of the case.

22

Page 22
Image 22
GE AZ75H18EAC, 49-7419-2 installation instructions 8FINAL CHECK, 9CONNECT POWER, Servicing, Installation Instructions