6 Termination Locations

6 Termination Locations

A. Vent Termination Minimum Clearances

A. Vent Termination Minimum Clearances WARNING

Fire Risk.

Maintain vent clearance to combustibles as specified.

DO NOT pack air space with insulation or other materials.

Failure to keep insulation or other materials away from vent pipe may cause overheating and fire.

A

B

6 in. (minimum) up to 20 in.

18 in. minimum

152 mm/508 mm

457 mm

20 in. and over

0 in. minimum

Gas, Wood or Fuel Oil

Termination Cap

B

A*

Î

LISTED B-VENT TERMINATION CAP

8 FEET

VERTICAL

 

WALL

LOWEST

DISCHARGE

OPENING

X

12

Figure 6.2 Staggered Termination Caps ROOF PITCH

IS X/ 12

H (MIN.) - MINIMUM HEIGHT FROM ROOF TO LOWEST DISCHARGE OPENING

Gas

Termination

Cap **

*If using decorative cap cover(s), this distance may need to be increased. Refer to the installation instructions supplied with the decorative cap cover.

**In a staggered installation with both gas and wood terminations, the wood termination cap must be higher than the gas termination cap.

Figure 6.2 Staggered Termination Caps

Roof Pitch

H (Min.) Ft.

Flat to 6/12

1.0*

Over 6/12 to 7/12

1.25*

Over 7/12 to 8/12

1.5*

Over 8/12 to 9/12

2.0*

Over 9/12 to 10/12

2.5

Over 10/12 to 11/12

3.25

Over 11/12 to 12/12

4.0

Over 12/12 to 14/12

5.0

Over 14/12 to 16/12

6.0

Over 16/12 to 18/12

7.0

Over 18/12 to 20/12

7.5

Over 20/12 to 21/12

8.0

* 3 foot minimum in snow regions

Figure 6.1 Minimum Height From Roof To Lowest Discharge Opening

22

Heat & Glo • SL-550 / 750 / 950TV-IPI-E2119-900 Rev. J • 12/09

Page 22
Image 22
Heat & Glo LifeStyle SL-750TV-IPI-E owner manual Termination Locations, A. Vent Termination Minimum Clearances, Roof Pitch