Installation and Operations Manual
Rigging
CAUTION: Avoid contact with sharp edges and coil surfaces. They are a potential injury hazard. Wear gloves during moving and rigging.
Caution should be exercised when moving these units. To prevent damage to the unit housing during rigging, cables or chains used must be held apart by spacer bars. Rigging holes are provided on all models. See FIGURES 10 and 11.
Figure 10: Rigging Holes
Figure 11: Rigging Holes Front View
Rigging holes
Mounting |
The system requires two
Through bolts should be insulated or
1.Install two through bolts to secure the unit to the wall. The inside of the box should be reinforced with wood or metal for proper when mounting of the unit to the box with through bolts.
2.Install and secure the roof of the box. Inside the box, provisions have been made to secure the evaporator section to the roof panel with through bolts.
3.The area between the evaporator section and the roof panel should be caulked to meet NSF codes. In addition, the openings where the unit was lowered into the box panel should be caulked to prevent any infiltration from the outside area into the box.
4.Ensure that the condensing unit airflow is not obstructed after removing the temporary support.
5.Do not obstruct the evaporator airflow with shelving. The area below the evaporator should be left completely open.
6.Connect unit to power supply through
7.Apply power to unit. All controls are preset to factory default settings. See Table 1 (next page).
8.Check the unit for proper operation.
Figure 12: Mounting Holes Side View
Mounting holes
FIGURE 13: Mounting Holes Front View
Mounting holes
Front panels |
removed |
for clarity |
Mounting |
holes |
FIGURE 14: Mounting Holes Top View
Top not shown | Mounting holes |
for clarity |
|