PRO3 Side Mount Packaged Refrigeration System
Inspection
1.Each shipment should be carefully checked against the bill of lading.
2.The shipping receipt should not be signed until all items listed on the bill of lading have been accounted for.
3.Check packaging for signs of damage.
4.Any shortage or damages should be immediately reported to the delivering carrier.
5.Damaged material becomes the delivering carrier’s responsibility, and should not be returned to the manufacturer unless prior approval is given to do so.
6.All units are shipped on heavy skids and enclosed in open crating. Generally, it is advisable to bring the unit as close to its final location as possible before removing crating.
7.When unpacking the system, care should be taken to prevent damage.
8.Avoid removing the shipping base until the unit has been moved to the final destination.
Installation Requirements
Recommended Unit Placement
1.Ensure that the structural integrity of the box can withstand the weight of the
2.The air pattern must cover the entire room
3.Location of aisles, racks, etc. must be known
4.For space requirements, see FIGURES 1 and 2
Figure 1: System Space Requirements Back View
Leave this area unobstructed
Figure 2: System Space Requirements Side View
24" |
Leave these areas unobstructed
Access Requirements
Condensing Unit Section (Exterior of box)
Provide adequate access space (minimum 36") on the right side of the unit for electric box clearance. The front of the unit should have a minimum of 24" clearance for compressor and fan motor service. The left side of the unit should be a minimum of 8" clearance.
Figure 3: Access Requirements Top View
18" |
|
|
|
|
|
|
|
|
|
|
|
| 18" |
|
|
|
|
|
|
|
|
|
|
| |||
|
|
|
|
|
|
|
|
| |||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
36" |
8" |
24" |
Evaporator Section (Interior of box)
The front of the evaporator should have no obstructions since this is the leaving airside of the evaporator. There should also be no obstructions under the evaporator. A minimum of 8" clearance should be held on each side of the evaporator for drain pan removal.
PRO3 Side Mount Packaged Refrigeration System Installation and Operations Manual, May 2008 | 3 |