Installation & Operation Manual
3 Sidewall direct venting (continued)
Prepare wall penetrations (Alternate Field Supplied Options)
1.Air pipe penetration (see FIG.
a.Cut a hole for the air pipe. Size the air pipe hole as close as desired to the air pipe outside diameter.
2.Vent pipe penetration (see FIG.
a.Cut a hole for the vent pipe. For either combustible or noncombustible construction, size the vent pipe hole with at least a 1/2 inch clearance around the vent pipe outer diameter:
•7½ inch (178 mm) hole for 6 inch (152 mm) vent pipe
•8½ inch (203 mm) hole for 7 inch (178 mm) vent pipe
b.Insert a galvanized metal thimble in the vent pipe hole (when required by local codes).
3.Use a sidewall termination plate as a template for correct location of hole centers.
4.Follow all local codes for isolation of vent pipe when passing through floors or walls.
5.Seal exterior openings thoroughly with exterior caulk.
Figure
SIDEWALL | GALVANIZED |
THIMBLE (WHEN REQUIRED BY LOCAL CODES) | |
TERMINATION PLATE | ELBOW |
| |
VENT |
|
PIPING | AIR PIPING |
BIRD SCREEN
ELBOW
BIRD SCREEN
Multiple vent/air terminations
1.When terminating multiple SYNC boilers terminate each vent/air connection as described in this manual (FIG.
WARNING All vent pipes and air inlets must terminate at the same height to avoid
possibility of severe personal injury, death, or substantial property damage.
2.Place wall penetrations to obtain minimum clearance of 12 inches (305 mm) between vent pipe and adjacent air inlet elbow, as shown in FIG.
3.The air inlet of a SYNC is part of a direct vent connection. It is not classified as a forced air intake with regard to spacing from adjacent boiler vents.
Figure
12" MIN. BETWEEN EDGE OF AIR INLET AND ADJACENT VENT OUTLET
VENT
AIR
VENT / AIR
TERMINATION
Figure
VENT
12” (305 MM) MIN 15” (381 MM) MAX
12” (305 MM) MIN. BETWEEN EDGE OF AIR PIPE AND ADJACENT VENT PIPE