11 Maintenance (continued)

Cleaning boiler heat exchanger

For recommended materials; including brush, appropriate extension(s), refractory cover, and detailed instructions see Table 11B - Heat Exchanger Cleaning Kits.

1.Shut down boiler:

Follow the “To Turn Off Gas to Appliance” instructions for the boiler in Section 9 - Startup.

Do not drain the boiler unless it will be exposed to freezing temperatures. If using freeze prevention fluid in system, do not drain.

2.Allow time for the boiler to cool to room temperature if it has been firing.

3.Remove the nuts securing the heat exchanger access cover to the heat exchanger and set aside.

4.Remove the heat exchanger access cover, burner, and gas/air arm assembly.

￿WARNING The boiler contains ceramic fiber materials. Use care when handling these materials

per instructions on page 62 of this manual. Failure to comply could result in severe personal injury.

5.Remove the condensate hose from the heat exchanger end. Connect a field supplied 3/4" diameter hose to a drain pan. Using field supplied means, cover the refractory in the back of the combustion chamber of the heat exchanger.

6.Use a vacuum cleaner to remove any accumulation on the boiler heating surfaces. Do not use any solvent.

7.Brush the heat exchanger while dry using a nylon bristle brush. Caution: DO NOT use a metal brush. Re-vacuum the heat exchanger.

8.Finish cleaning using a clean cloth dampened with warm water. Rinse out debris with a low pressure water supply.

9.Allow the heat exchanger to thoroughly dry.

10.Remove the field supplied rear refractory cover from the back of the combustion chamber of the heat exchanger and reassemble.

11.Close isolation valves on piping to isolate boiler from system. Attach a hose to the boiler drain and flush boiler thoroughly with clean water by using purging valves to allow water to flow through the water make-up line to the boiler.

12.Perform start-up and check-out procedures in the Check Flame and Combustion - Section 9 - Startup on pages 45 and 47 of this manual.

13.Replace the access cover and restore boiler to operation.

Installation & Operation Manual

Table 11B

Heat Exchanger Cleaning Kits

 

 

 

 

 

Model

 

Kit

Part

Component

Number

 

Number

Number

Description

 

 

 

 

 

 

 

 

MSC20083*

Nylon 4" Wheel Brush*

 

 

 

 

SB 1.0 - 1.5

KIT30064

MSC20085

1/4" x 12" Drill Extension

 

 

 

 

 

 

 

 

MSC20086

1/4" x 24" Drill Extension

 

 

 

 

 

￿CAUTION * Do NOT use a metal brush. Only use the kit provided brush or an equivalent

replacement nylon brush.

Figure 11-3Rope Gasket - Heat Exchanger Door

ROPE GASKET

CAUTION: IF GASKET IS DAMAGED

DO NOT REUSE, THE HEAT EXCHANGER DOOR

MUST BE REPLACED.

Rope gasket is intended for sealing combustion NOTICE (FIG. 11-3). If damaged DO NOT reuse, the

heat exchanger door must be replaced. Consult factory for replacement heat exchanger door (kit WTR3086).

Table 11B 61 Heat Exchanger Cleaning Kits