4 Vertical direct venting (continued)
Multiple vent/air terminations
1.When terminating multiple SYNC boilers, terminate each vent/air connection as described in this manual (FIG.
WARNING Terminate all vent pipes at the same height and all air pipes at the same height to
avoid recirculation of flue products and the possibility of severe personal injury, death, or substantial property damage.
2.Place roof penetrations to obtain minimum clearance of 12 inches (305 mm) between edge of air intake elbow and adjacent vent pipe of another boiler for U.S. installations (see FIG.
3.The air inlet of a SYNC boiler is part of a direct vent connection. It is not classified as a forced air intake with regard to spacing from adjacent boiler vents.
Figure
12" (305 MM) MINIMUM VERTICALLY FROM VENT OUTLET TO ANY AIR INLET
|
| VENT |
| AIR | 12" (305 MM) MINIMUM FROM EDGE |
|
| |
VENT |
| OF AIR INTAKE PIPE TO ADJACENT |
AIR |
| VENT PIPE FROM ANOTHER BOILER |
|
|