FIREPLACE INSTALLATION | DFX & DBX Series Vent Free Fireplaces |
If unit is to be “built in”, fireplace framing can be built before or after the appliance is set in place. BE SURE THAT ALL
PACKING MATERIAL HAS BEEN REMOVED FROM THE UNDERSIDE OF THE UNIT PRIOR TO SETTING THE FIREBOX IN PLACE. Construct fireplace framing following Figure 2 on Page 6 for fireplace dimensions. The framing headers may rest directly on top of the firebox.
The fireplace may be installed directly on a combustible floor or a raised platform of an appropriate height. Do not place fireplace on carpeting, vinyl, tile or other soft floor coverings. It may, however, be placed on flat wood, plywood, particle board or other hard surfaces. Be sure fireplace rests on a solid continuous floor or platform with appropriate framing for support and so that no cold air can enter from under the firebox.
Anchor fireplace to the side framing members using nail- ing flanges.
| WARNING | The fireplace must be installed giving full |
|
| |
|
| consideration to the clearance and height |
|
| requirements identified in this manual. |
|
|
|
K
J
FP2445
When finishing a custom cabinet, mantel or other
Ref. | DFX24C | DBX24C | DFX32C |
J | 26C\v" | 26C\v" | 31Z\v" |
| (680 mm) | (680 mm) | (800 mm) |
K | 25" | 5" | 32ZC\zn" |
| (635 mm) | (635 mm) | (833 mm) |
Figure 7 -
Custom Cabinet
1.Bend out the nailing flanges located on each side of the firebox.
2.Slide the firebox into prepared framing or position firebox in its final position and frame later.
3.Level the firebox by checking the top edge of the firebox. Shim if necessary.
4.Anchor firebox to the side framing members using 8d nails or other suitable fasteners. Figure 8
5.The canopy must be installed for safe operation of the heater. Refer to Page 17 for canopy installation details.
Nail Sides |
Through Nailing |
Flanges |
FP2509 |
Figure 8 -
Nailing Flanges
33D4047 | 11 |