Amplifier Setup |
Forward Path Alignment
You must perform the following BT100 alignment procedures for proper performance in the forward path:
Select the appropriate cable equalizer or cable simulator
Select the appropriate input, midstage, and output pads
Verify proper flatness control
Verify proper level control
Before You Begin
Before you begin to
For proper forward alignment obtain:
RF output levels and tilts of all BT100s in the forward or return path
RF input level for the BT100 being set up (from system design or
A carrier at the system’s highest frequency. It can be modulated or continuous wave (CW) and should be inserted in the headend at standard video levels. This carrier is used to simplify field
It is recommended that you:
Install the system design value
Leave the forward input pad location open if a high value pad is not available. A more accurate forward input test point reading is achieved with a high value pad installed.
Do not remove or install the electronics chassis cover while the BT100 is powered.
If you need to remove or install the electronics chassis cover for any reason, shut off the AC power first. Verify that all chassis cover screws are tightened to
Do not use wire jumpers to bypass the
Recognize that actual pad and
Secure the electronics chassis in the housing and torque to 18 to 22
Perform a bench alignment.
Field sweep the entire bandwidth of the amplifier to correct frequency response for passive signature and
Close the housing in accordance with the instructions in Section 5, “Installation.”