- 106 -

List of terms

processor card section

The section of the shelf assembly that contains processor cards and the backplane that allows the processor cards to communicate with each other.

processor control system (PCS)

Nortel Multiservice Switch subsystem responsible for managing the processor cards. PCS detects when a processor becomes available for service, maps the appropriate LP to execute on it, loads its software, and monitors its execution to detect any outage that occurs. If an outage occurs, PCS invokes the appropriate recovery procedures (such as restarting the software or switching over to a spare processor card).

processor module (PM)

The part of some processor cards that handles the processing requirements for a control processor (CP) and a function processor (FP).

product engineering code (PEC)

The product engineering code (PEC) of Nortel Networks hardware identifies the part number of equipment or a set of components that combine to make an assembly or a unit. The PEC is used by hardware installers to verify the correct installation, replacement, or upgrade of equipment.

propagation delay

Is the time it takes one bit of information to travel along a transmission medium from one device (Nortel Multiservice Switch node) to its neighbor device (Multiservice Switch node). Propagation delay is a function of the speed of an electrical (optical) signal and the distance to be travelled.

protected default route (PDR)

A protected default route is a static route to the default route 0.0.0.0, provisioned as ‘protected’, and provisioned with multiple nextHops, each using a unique local IP interface. Because a PDR is protected, the operational states of these nextHops/interfaces are monitored, and the forwarding information for this route is optimally managed to enable route reprogramming within 1 second in the case of an active nextHop/interface failure. A protected default route is only supported for a non-ECMP default static route.

protected static route

A protected route is a non-ECMP IP route with a set of nextHops (each using unique local IP interfaces) which can be used to forward the packet. The operational state of these nextHops/interfaces are monitored, and the forwarding information is optimally managed to enable route reprogramming within 1 second in the case of an active nextHop/interface failure.

Nortel Multiservice Switch 7400/15000/20000

Terminology

NN10600-005 7.2S1 Standard

PCR7.2 and up March 2006

Copyright © 2006, Nortel

Nortel Confidential

Page 106
Image 106
Panasonic 15000 Processor card section, Processor control system PCS, Processor module PM, Product engineering code PEC