Potthof & Co 24kw 7.0Site Requirement, metre, Minimum, fall, 50mm per, 7.7Condensate Drain cont

Models: 24kw 28kw 33kw

1 64
Download 64 pages 28.28 Kb
Page 18
Image 18
7.7Condensate Drain (cont.)

iii) Termination to a drain or gully

Boiler

Pipe must terminate above water level but below surrounding surface. Cut end at 45°

50mm

per

 

 

 

 

 

metre

 

2.

of pipe

run

 

 

Minimum

 

 

 

fall

 

7.0Site Requirement

7.7Condensate Drain (cont.)

11.When discharging condensate into a soil stack or waste pipe the effects of existing plumbing must be considered. If soil pipes or waste pipes are subjected to internal pressure fluctuations when WC's are flushed or sinks emptied then back-pressure may force water out of the boiler trap and cause appliance lockout.

Boiler

iv)Termination to a purpose made soakaway Further specific requirements for soakaway design are referred to in BS 6798.

50mm per 500mm min

50mm per

 

metre of

2.5°

pipe run

Minimum fall

 

Holes in the soak-away must face away from the building

18© Baxi Heating UK Ltd 2012

Page 18
Image 18
Potthof & Co 24kw, 33kw, 28kw manual 7.0Site Requirement, Minimum, fall, 50mm per, 7.7Condensate Drain cont, metre of