INSTALLATION
HORIZONTAL
INSTALLATIONS
Install the vent system according to the manufacturer's instructions included with the components.
1)Set the unit in its desired location. Check to determine if wall studs or roof rafters are in the way when the venting system is at- tached. If this is the case, you may want to adjust the location of the unit. Rough in the gas preferably on the right side of the unit and the electrical (junction block is on the left side) on the left.
2)Direct Vent pipe and fi ttings are designed with special
3)Put a bead of silicone inside the outer sec- tion of the adapter and a bead of Mill Pac on the inner collar. Slip the adapter over the existing inner and outer flue collar and fasten to the outer collar only with the 3 supplied screws (drilling pilot holes will make this easier). Level the fi replace and fasten it to the framing using nails or screws through the nailing strips.
4)Assemble the desired combination of pipe and elbows to the appliance adaptor and
Note:
a)
Diagram 1
Note: Apply sealant
b)Horizontal runs of vent must be supported every three feet. Wall straps are available for this purpose.
5)Mark the wall for a 10" x 10" square hole. The center of the square hole should line up with the centerline of the horizontal pipe. Cut and frame the 10 inch square hole in the exterior wall where the vent will be terminated. If the wall being penetrated is
acceptable.
Note: With
t h e m i n i - mum height
is achieved by installing
a 90o elbow directly to the rigid pipe adaptor.
Diagram 2
Note:
a)The horizontal run of vent must be level, or have a 1/4 inch rise for every 1 foot of run towards the termination. Never allow the vent to run downward. This could cause high temperatures and may present the possibility of a fi re.
b)The location of the horizontal vent ter- mination on an exterior wall must meet all local and national building codes, and must not be blocked or obstructed. For External Vent Terminal Locations, see diagram on page 10.
c)Snorkel Terminations:
For installations requiring a vertical rise on the exterior of the building,
are available, as well as the standard Riser Vent. Follow the same installation procedures as used for stand- ard Horizontal Termination .
N E V E R install the
s n o r k e l u p s i d e down.
Diagram 3
Note: Riser Vent is only for use in above grade terminations.
Diagram 3a
*Diagrams 3 & 4: As specified in CGA B149 Installation Code. Local codes or regulations may require different clearances.
Below Grade Installation
If the Snorkel Termination must be installed below grade, i.e. basement application, proper drainage must be provided to prevent water from entering the Snorkel Termination. Refer to Diagram 4. Do not attempt to enclose the Snorkel within the wall, or any other type of enclosure.
Diagram 4
NOTE: For Snorkel terminations in ABOVE grade installations, follow national or local code requirements.
6)The arrow on the vent cap should be pointing up. Insure that the
20 | UltraGlow G36D Zero Clearance Direct Vent Gas Fireplace |