SECTION 5: HEATER INSTALLATION 5.1 General

SECTION 5: HEATER INSTALLATION

SECTION 5: HEATER INSTALLATION 5.1 General

Heaters are designed for floor standing vertical installation. Special versions supplied with steel channels to support the heater are available and may be mounted horizontally. When installed horizontally, the heater will normally lie on its left side when viewed from the burner. The heater

should be placed on a firm, level, non-combustible surface that can support its weight. See Page 5, Section 4.1 for weight details.

5.2 Handling

All cabinet heaters are supplied secured to a wooden pallet and shrink wrapped. Use the pallet to support the heater during handling and installation.

Figure 2: Typical Installation of a Gas Fired Cabinet Heater

 

Flues up to 200 mm dia. are

 

fitted with Bird Screens, over

1 m

200 mm with a Rain Cap.

 

Minimum

 

 

Lead Roof Plate

Flue

 

Air

 

Distribution

Roof

Heads

 

Building Ventilation

Electric Supply

Gas Isolating Valve

Union

Connection