SSE 5 BL

8.2. Mounting on the processing machine

A material hopper VT 2,3/70 / VT 2,8/70 is required: Mount the material hopper onto the flange of the processing machine.

Mount the unit onto the material hopper.

F Figure 6: VT 2,3/70 / VT2,8/70

Observe the bearing capacity of the machine flange.

8.3. Mounting onto a machine hopper

A welding flange EF 190 or an assembly flange MF 253 is required:

LPlease observe all safety regulations for the operation of welding equipments.

Always wear a safety goggle.

Weld the welding flange into the machine hopper lid. Mount the unit onto the flange.

Or

Mount the assembly flange.

Mount the unit onto the flange.

Figure 6: EF 253

Figure 6: MF 253

Assembly instructions 24

Page 38
Image 38
Sterling SSE-5 BL operating instructions Mounting on the processing machine, Mounting onto a machine hopper