Construct the Framing (cont.)

Construct the Framing (cont.)

Studs must be positioned roughly as shown in the ″Roughing-In″ section to properly fasten the attachment clips or the bath flange. Other stud locations are optional except for those which must meet the load-bearing requirements of local building codes. Studs must also allow for the installation of plumbing fittings and any shower door. Locate the shower door studs as required by the shower door manufacturer.

For Bath with Apron Flanges

If apron flanges are in place on the apron, ensure that the outer stud is positioned for the apron flanges at 31-1/4″ (79.4 cm) from the back wall. The outer edge of the stud should align with the edge of the apron flange.

If the apron flanges are not going to be used or are broken, install three evenly distributed 2x4 blocks just behind the apron location. The blocks will prevent the apron from being damaged and may be used to secure the apron behind the baseboard. Measure the bath for the required clearance behind the apron and for the location of the blocks.

For Bath with Wall Surrounds

NOTE: If the wall surrounds will be installed to a masonry wall, make provisions for plumbing connections. For the plumbing end wall, construct a separate frame wall a minimum of 6″ (15.2 cm) from the masonry wall. For the remaining walls, use 2x2 furring strips to provide stud locations.

Ensure that the outer stud is positioned with the vertical wall flanges 31-1/4″ (79.4 cm) from the back wall. The outer edge of the stud should align with the edge of the wall flange.

IMPORTANT! Accessories that require backing or support are not recommended for this installation. Installing these accessories could void the warranty.

Ensure fiber or other soft insulation does not drop down into the water channel. Cover or seal any loose material. Failure to do so may cause wicking of water from the water channel into the insulation which may induce mold, leakage, or mildew. Ensure the channels are free of debris after installation.

For Above-the-Floor Drain Baths

Ensure the drain piping can pass through the wall and that the load bearing requirements of the wall are satisfied. Modify the framing or raise the subfloor as required to obtain clearance.

For All Installations

Construct 2x4 stud framing for your particular installation according to the ″Roughing-In″ section.

Ensure that the framing for each stud is plumb and square within 1/8″ (3 mm). Shimming will be required if tolerances are not met.

If possible, construct an access panel in the plumbing end wall to simplify future maintenance of all plumbing connections.

Construire le cadrage

REMARQUE: Se référer à la section ″Raccordement″ pour les dimensions.

Provisions cadrage

AVERTISSEMENT: Risque d’endommagent du produit et de la propriété. La baignoire doit être supportée par le plancher. Les murs avoisinants ne sont pas désignés pour maintenir la baignoire en place et ne sont pas conçus pour un

supportde charge. Les clips ou clous pour toiture doivent être utilisés pour éviter un mouvement latéral de la baignoire.

La baignoire avec bandeau doit être fixée aux montants sur trois côtés.