INSTALLATION INSTRUCTIONS
INSTALLATION
3.16It is now necessary to connect the gas supply to the appliance. The gas supply may enter through the floor directly under the appliance or through the knockout panel in the rear RH corner of the outer casing. In both instances, a preformed pipe is ready fitted and connection should be made to the compression fitting on the end of this pipe. See diagram 10.
10
AR1294
3.17Ensure the front door is open by depressing centrally on the RH side; remove the glass frame assembly by unscrewing the nine retaining screws. See diagram 11.
11
3.19Connect a suitable pressure gauge to the test point located on the inlet fitting and turn the gas supply on. Check all connections for leaks paying particular attention to the fittings at each end of the inlet pipe. See diagram 12.
12
AR1294
3.20Light the appliance and check the rest of the joints for leaks. Turn the appliance to maximum and check the supply pressure is as stated on the databadge. Turn the gas off and replace the test point screw, turn the gas back on and check the test point for leaks.
AR0816
3.18Carefully remove the box containing the logs and place to one side. Remove the cardboard fitment that protects the factory fitted ceramic panels; take care as these are easily damaged.