10.RUN-IN OPERATION OF ENGINE after REASSEMBLY

An overhauled engine must be carefully run-in to get proper engine surface conditions on newly installed parts. A thorough run-in operation is indispensable particularly when cylinder, piston, piston rings,or valves are replaced.

The recommended run-in schedule is as tabulated below.

 

LOAD

 

SPEED

TIME

EY33-2

EY44-2

 

 

 

I

 

I

I

No load

No load

2500 r.p.m.

10 minutes

No load

No load

r.p.m.

10 minutes 3000

No load

No load

r.p.m.

10 minutes 3600

3.25

HP

4 HP

3600 r.p.m.

30 minutes

6.5

HP

8 HP

r.p.m.

60 minutes 3600