| Flue Gas Analysis System | Theory of Operation 2 | |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2.2Combustible Analyzer
The detector assembly and resistors R7 and R8 form a Wheatstone Bridge. The signal for the bridge is taken from the junction of R7 and R8 for the reference signal which is applied to
The ZERO adjustment is made at the potentiometer P1. The adjust- ment is made by unbalancing the bridge. Potentiometer P1 is connected to the same supply voltage as the bridge with resistor R9 connected to the center of the reference side of the bridge. This arrangement provides sufficient unbalance voltage to compensate for the unbalance of the sensor.
Amplifier A1 is set up with a gain of about 20, nominally for 5% methane. The output at
ALARM potentiometer P3 is the setpoint adjustment for the alarm. When the output from the gas amplifier goes higher than the setting of P3, transistor Q1 is turned on and relay K2 is energized, resulting in an alarm. A BUZZER toggle switch, when placed in the ALARM setting, allows an internal buzzer to sound, indicating that the unit has gone into alarm. Additionally, illumination of a red ALARM light indicates an alarm (while illumination of the green SAFE light indicates normal operation). If the AUTO/MAN toggle switch is set to MAN, the alarm latches and it is necessary to switch to Al, to AUTO to unlatch the alarm.
As noted previously, relay K2 is energized when an alarm occurs. With no alarm, the normally closed contact is closed and the normally open contact is open. When an alarm condition occurs, the contacts transfer and reverse their normal state.
TELEDYNE BROWN ENGINEERING |
Analytical Instruments