LEVER ARM ASSEMBLY
(ALL MODELS)
Upper
WARNING: SHUT OFF THE GAS BEFORE SERVICING.
WARNING: ALL GAS JOINTS DISTURBED DURING SERVICING MUST BE CHECKED FOR LEAKS. CHECK WITH SOAP AND WATER SOLUTION (BUBBLES). DO NOT USE AN OPEN FLAME.
1.Remove the grid carriage assembly as outlined in Grid Carriage Assembly.
2.Remove the two cotter pins and washers from the upper lever arm assembly.
3.Remove the upper lever arm assembly from the two brackets.
4.Reverse the procedure to install.
Lower
WARNING: SHUT OFF THE GAS BEFORE SERVICING.
WARNING: ALL GAS JOINTS DISTURBED DURING SERVICING MUST BE CHECKED FOR LEAKS. CHECK WITH SOAP AND WATER SOLUTION (BUBBLES). DO NOT USE AN OPEN FLAME.
1.Remove the grid carriage assembly as outlined in Grid Carriage Assembly.
2.Remove two screws and the lower lever cover from the broiler.
– 25 –