TABLE 19: INDOOR BLOWER SPECIFICATIONS

035-19046-002-B-0104

TABLE 19: INDOOR BLOWER SPECIFICATIONS

MODEL

 

 

MOTOR

 

 

MOTOR SHEAVE

 

BLOWER SHEAVE

 

BELT

 

 

 

 

 

 

 

 

 

 

 

 

 

HP

RPM

Eff.

 

SF

Frame

Datum Dia. (in.)

Bore (in.)

Model

Datum Dia. (in.)

Bore (in.)

Model

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DJ150

3

1725

80%

 

1.15

56

3.4 - 4.4

7/8

1VM50

7.0

1

AK74

A54

 

 

 

 

 

 

 

 

 

 

 

 

 

5

1725

87%

 

1.15

184T

4.3 - 5.3

1 1/8

1VP56

6.7

1

BK77

BX55

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AIR BALANCE

Start the supply air blower motor. Adjust the resistances in both the supply and the return air duct systems to balance the air distribution throughout the conditioned space. The job specifications may require that this balancing be done by someone other than the equipment installer.

CHECKING AIR QUANTITY

METHOD ONE

1.Remove the dot plugs from the duct panel (for location of the dot plugs see Figure 9).

2.Insert eight-inches of 1/4 inch metal tubing into the air- flow on both sides of the indoor coil.

NOTE: The tubes must be inserted and held in a position perpendicular to the air flow so that velocity pres- sure will not affect the static pressure readings.

METHOD TWO

1.Drill two 5/16 inch holes, one in the return air duct as close to the inlet of the unit as possible, and another in the supply air duct as close to the outlet of the unit as possible.

2.Insert eight inches of 1/4 inch metal tubing into the air- flow of both return and supply air ducts of the unit.

NOTE: The tubes must be inserted and held in position per- pendicular to the airflow so that velocity pressure will not affect the static pressure readings.

3.Use an Inclined Manometer or Magnehelic to determine the pressure drop across a dry evaporator coil. Since the moisture on an evaporator coil can vary greatly, measur- ing the pressure drop across a wet coil under field condi- tions could be inaccurate. To assure a dry coil, the compressors should be de-activated while the test is being run.

NOTE: De-energize the compressors before taking any test measurements to assure a dry evaporator coil.

4.The CFM through the unit with clean 2 inch filters can be determined from the pressure drop indicated by the manometer by referring to Figure 25.

5.To adjust Measured CFM to Required CFM, see ’SUP-

PLY AIR DRIVE ADJUSTMENT’.

3.Use an Inclined Manometer or Magnehelic to determine the pressure drop across the unit. This is the External Static Pressure (ESP).

4.Select the indoor blower specifications for the unit from Table 19, 3 or 5 H.P. Motor.

5.Determine the number of turns the variable pitch motor sheave is open.

6.Select the correct blower performance table for the unit from Tables 15 - 18.

7.Determine the unit Measured CFM from the Blower Per- formance Table, External Static Pressure and number of turns the variable pitch motor sheave is open.

8.To adjust Measured CFM to Required CFM, see ’SUP-

PLY AIR DRIVE ADJUSTMENT’.

6.After adjustments have been completed, remove the tubes and replace the dot plugs.

9.After adjustments have been completed, remove the tubes and seal holes.

Failure to properly adjust the total system air quan- tity can result in extensive blower damage.

NOTE: With the addition of field installed accessories repeat this procedure.

Failure to properly adjust the total system air quan- tity can result in extensive blower damage.